Finding 505139 (2021-008)

Significant Deficiency Repeat Finding
Requirement
L
Questioned Costs
-
Year
2021
Accepted
2024-11-08

AI Summary

  • Issue: FFATA reports for multiple months were not submitted on time.
  • Impacted Requirements: Compliance with federal reporting deadlines was not met.
  • Recommended Follow-up: Ensure timely submission of future reports and review processes for compliance.

Finding Text

The required Federal Funding Accountability Transparency Act (FFATA) reports of August, September, October, November and December 2020 and for the months of January, March and May 2021 were not submitted within the required period.

Corrective Action Plan

The Program is designing and implementing policies and procedures to assure the submission of all performance and FFATA reports on time.

Categories

No categories assigned yet.

Other Findings in this Audit

  • 505134 2021-003
    Significant Deficiency Repeat
  • 505135 2021-004
    Significant Deficiency Repeat
  • 505136 2021-005
    Significant Deficiency Repeat
  • 505137 2021-006
    Significant Deficiency Repeat
  • 505138 2021-007
    Significant Deficiency Repeat
  • 1081576 2021-003
    Significant Deficiency Repeat
  • 1081577 2021-004
    Significant Deficiency Repeat
  • 1081578 2021-005
    Significant Deficiency Repeat
  • 1081579 2021-006
    Significant Deficiency Repeat
  • 1081580 2021-007
    Significant Deficiency Repeat
  • 1081581 2021-008
    Significant Deficiency Repeat

Programs in Audit

ALN Program Name Expenditures
97.036 Disaster Grants - Public Assistance (presidentially Declared Disasters) $643.01M
97.039 Hazard Mitigation Grant $5.83M
93.982 Mental Health Disaster Assistance and Emergency Mental Health $4.95M
97.047 Pre-Disaster Mitigation $48,543