Finding 400148 (2022-005)

Significant Deficiency Repeat Finding
Requirement
L
Questioned Costs
-
Year
2022
Accepted
2024-06-06
Audit: 308290
Organization: Puerto Rico Ports Authority (PR)
Auditor: Galindez LLC

AI Summary

  • Core Issue: Reports were submitted late, violating FAA regulations.
  • Impacted Requirements: Annual form SF-425 and Forms FAA 5100-126 and FAA 5100-127 were not filed on time.
  • Recommended Follow-Up: Implement a tracking system to ensure timely submission of all required reports.

Finding Text

Quarterly Performance Reports and Form SF‐425 & Late filing of reports required by FAA regulations Condition: During our audit procedures we identified the following instances: a. We identified one (1) instance in which the annual form SF‐425 for Grant 3‐72‐0008‐019‐2021 was due December 31, 2022, but was submitted on March 30, 2023. b. In four (4) instances, Forms FAA 5100‐126 and FAA 5100‐127 which applies for seven (7) of the nine (9) airports, and had a due date of October 31, 2022, were filed on February 9, 2023.

Corrective Action Plan

During 2023, the FFMO, in coordination with the Engineering Bureau, created and implemented an automated scheduling reminder system using MS Outlook. This system alerts all those responsible to turn in their reports (FFR & MPR) five (5) days prior to the period end, and on the day the quarter ends. This implementation, together with continuous monitoring of the FFMO personnel, should eliminate this situation.

Categories

No categories assigned yet.

Other Findings in this Audit

  • 400146 2022-003
    Significant Deficiency Repeat
  • 400147 2022-004
    Significant Deficiency Repeat
  • 400149 2022-004
    Significant Deficiency Repeat
  • 400150 2022-004
    Significant Deficiency Repeat
  • 400151 2022-006
    Significant Deficiency
  • 400152 2022-007
    Significant Deficiency
  • 400153 2022-008
    Significant Deficiency
  • 400154 2022-004
    Significant Deficiency Repeat
  • 400155 2022-006
    Significant Deficiency
  • 400156 2022-007
    Significant Deficiency
  • 400157 2022-008
    Significant Deficiency
  • 400158 2022-004
    Significant Deficiency Repeat
  • 976588 2022-003
    Significant Deficiency Repeat
  • 976589 2022-004
    Significant Deficiency Repeat
  • 976590 2022-005
    Significant Deficiency Repeat
  • 976591 2022-004
    Significant Deficiency Repeat
  • 976592 2022-004
    Significant Deficiency Repeat
  • 976593 2022-006
    Significant Deficiency
  • 976594 2022-007
    Significant Deficiency
  • 976595 2022-008
    Significant Deficiency
  • 976596 2022-004
    Significant Deficiency Repeat
  • 976597 2022-006
    Significant Deficiency
  • 976598 2022-007
    Significant Deficiency
  • 976599 2022-008
    Significant Deficiency
  • 976600 2022-004
    Significant Deficiency Repeat

Programs in Audit

ALN Program Name Expenditures
21.027 Coronavirus State and Local Fiscal Recovery Funds $20.14M
20.500 Federal Transit_capital Investment Grants $3.70M
20.507 Federal Transit_formula Grants $868,109
97.036 Disaster Grants - Public Assistance (presidentially Declared Disasters) $367,865
20.106 Airport Improvement Program $146,389