Finding 1182220 (2023-003)

Material Weakness Repeat Finding
Requirement
L
Questioned Costs
-
Year
2023
Accepted
2026-03-24

AI Summary

  • Issue: The Organization missed the deadline to submit its fiscal year 2023 single audit report.
  • Requirements Impacted: The report should be submitted within 9 months of the fiscal year-end.
  • Follow-Up: Implement procedures to ensure timely filing of future single audit reports.

Finding Text

Condition During our current year audit, we noted that the Organization did not submit its fiscal year 2023 single audit report to the Federal Audit Clearinghouse within 9 months of its fiscal year-end. Questioned Costs N/A Criteria The Organization is required to undergo and complete the Data Collection Form in connection with its single audit within 30 days after receipt of the auditor’s report or 9 months of its fiscal year-end, whichever comes first. Cause The Organization did not have procedures in place to have their financial records ready for audit within 9 months. Effect of Condition The filing deadline for the September 30, 2023 single audit was not met. Recommendation The Organization should develop procedures to ensure the timely filing of its single audit report to the Federal Audit Clearinghouse.

Corrective Action Plan

Name of Contact Person Lillian Harrison, Executive Director Management’s Response/Corrective Action The Organization will develop policies and procedures to ensure that the timely filing of its single audit report to the Federal Audit Clearinghouse. Proposed Completion Date September 30, 2026

Categories

No categories assigned yet.

Other Findings in this Audit

  • 1182218 2023-001
    Material Weakness Repeat
  • 1182219 2023-002
    Material Weakness Repeat
  • 1182221 2023-004
    Material Weakness Repeat
  • 1182222 2023-005
    Material Weakness Repeat
  • 1182223 2023-006
    Material Weakness Repeat

Programs in Audit

ALN Program Name Expenditures
93.432 ACL CENTERS FOR INDEPENDENT LIVING $1.16M
93.048 SPECIAL PROGRAMS FOR THE AGING, TITLE IV, AND TITLE II, DISCRETIONARY PROJECTS $49,000