Finding 1166832 (2025-004)

Material Weakness Repeat Finding
Requirement
N
Questioned Costs
-
Year
2025
Accepted
2025-12-29

AI Summary

  • Core Issue: The Authority did not provide evidence for the utility rate differences this fiscal year.
  • Impacted Requirements: According to 24 CFR section 982.517, the Authority must review and adjust utility allowances annually if rates change by 10% or more.
  • Recommended Follow-Up: The Authority should schedule annual reviews of utility rates, ensuring documentation includes rate comparisons and percentage changes.

Finding Text

2025-004 Review of Utility Rate Data Condition: The Authority failed to substantiate the rate difference incurred in the current fiscal year. Criteria: Per 24 CFR section 982.517, the Authority must review utility rate data for each utility category each year and must adjust its utility allowance schedule if there has been a rate change of 10% or more for a utility category or fuel type since the last time the utility allowance schedule was revised. Context: While reviewing the utility allowance studies to determine whether there was a 10% or more change in utility costs, we were unable to gather backup documentation from the PHA to analyze the utility costs. Effect: Due to the inability to determine the amount of change in utility costs, the PHA may have implemented inaccurate utility allowances which may have resulted in incorrect HAP payments. Recommendation: We recommend that the Authority list the required procedure on their annual calendar to verify that the utility rate data is analyzed, documented, and change as necessary. Documentation must include the comparison of the rates of the established utility rates to the current utility rates and the percent of change. Response: BPHA has already engaged a qualified third-party vendor to assist with the analysis and update of the Utility Allowance schedule to ensure compliance with HUD requirements. We will ensure supporting documentation is maintained. Compliance will be monitored through internal control processes to ensure annual reviews are completed timely and properly documented.

Corrective Action Plan

BPHA has already engaged a qualified third-party vendor to assist with the analysis and update of the Utility Allowance schedule to ensure compliance with HUD requirements. We will ensure supporting documentation is maintained. Compliance will be monitored through internal control processes to ensure annual reviews are completed timely and properly documented.

Categories

HUD Housing Programs

Other Findings in this Audit

  • 1166831 2025-003
    Material Weakness Repeat
  • 1166833 2025-005
    Material Weakness Repeat
  • 1166834 2025-006
    Material Weakness Repeat
  • 1166835 2025-007
    Material Weakness Repeat

Programs in Audit

ALN Program Name Expenditures
14.871 SECTION 8 HOUSING CHOICE VOUCHERS $4.07M
14.879 MAINSTREAM VOUCHERS $511,638
14.850 PUBLIC HOUSING OPERATING FUND $247,510
14.872 PUBLIC HOUSING CAPITAL FUND $219,965