Finding 986242 (2022-001)

-
Requirement
C
Questioned Costs
-
Year
2022
Accepted
2023-08-30
Audit: 311942
Organization: Rodsewood Housing Corporation (MO)

AI Summary

  • Core Issue: The Project failed to make the required monthly deposits to the reserve for replacement account, resulting in a $480 shortage.
  • Impacted Requirements: Monthly deposits must align with HUD guidelines, which were not met for 11 months.
  • Recommended Follow-Up: Management should prioritize funding the reserve shortage as soon as possible.

Finding Text

Finding 2022-001- Replacement Reserve DepositsCondition Found The Project only made 11 months of deposits for a total of $5,760. The deposits should have totaled $6,240.Criteria: According to HUD?s guidelines, a Project must make monthly deposits to the reserve for replacement account.Cause: Project management did not make the required monthly deposit, causing a shortage in the reserve for replacement account for the year ending June 30, 2022.Effect The Project held excess cash and did not make the required deposit.Recommendation: The overall reserve shortage of $480 should be funded as soon as possible.Current Status Management will fund the reserves as soon as funds are available.

Categories

Cash Management HUD Housing Programs

Other Findings in this Audit

Programs in Audit

ALN Program Name Expenditures
14.181 Supportive Housing for Persons with Disabilities $1.38M
14.195 Section 8 Housing Assistance Payments Program $60,084