Finding 516538 (2024-004)

Material Weakness
Requirement
N
Questioned Costs
-
Year
2024
Accepted
2024-12-23

AI Summary

  • Core Issue: The Authority failed to complete a required environmental review since 2015, exceeding the five-year limit.
  • Impacted Requirements: Compliance with environmental review procedures outlined in PIH Notice 2016-22 HA and 24 CFR parts 50 and 58.
  • Recommended Follow-Up: Establish a proactive system to ensure timely environmental reviews for all future capital fund projects.

Finding Text

Finding 2024-004: Environmental Review Capital Funds – 14.872 Material Weakness/Noncompliance – Special Tests and Provisions Criteria: An environmental review must be completed for any project or activities before a PHA may acquire, rehabilitate, convert, lease, repair, or construct property, or commit HUD or local funds at an assisted or to-be-assisted site. Environmental review procedures for PHAs are given in PIH Notice 2016-22 HA, “Environmental Review Requirements for Public Housing Agencies.” The environmental reviews are not tied to specific grants but apply to all the operating and capital activities of the PHA for a five-year period. The Notice cites the governing regulations at 24 CFR parts 50 and 58 and describes the methods of review and types of determinations. All of these methods and types culminate in a final approval document signed by a HUD Approving Official. To be in compliance a PHA must have such an approval document with an approval date that is not over five years old. Condition: The last environmental review the Authority was able to provide was done in 2015 and was beyond the requirement of having an environmental review that is not more than five years old. Cause: The Authority did not have a system in place to ensure it had a current environmental review. Effect or Potential Effect: The Authority did not comply with the environmental review requirements. Recommendation: The Authority should establish a system to be proactive in ensuring it has a current environmental study covering future projects funded by capital fund grants. View of the Responsible Officials of the Auditee: The auditee's management agrees with the finding.

Corrective Action Plan

The Authority is aware of the Environmental Review requirement. However, during Covid 19, we received an email stating it was not required. Therefore, the last one was past the five-year requirement. It is procedure to conduct an Environmental Review when the Authority does its Five-Year Capital Funds Plan. Therefore, the Authority will conduct a review this year for calendar years 2025-2029.

Categories

HUD Housing Programs Material Weakness Special Tests & Provisions

Other Findings in this Audit

  • 516536 2024-002
    Material Weakness
  • 516537 2024-003
    Material Weakness
  • 1092978 2024-002
    Material Weakness
  • 1092979 2024-003
    Material Weakness
  • 1092980 2024-004
    Material Weakness

Programs in Audit

ALN Program Name Expenditures
14.872 Public Housing Capital Fund $450,037
14.850 Public and Indian Housing $168,510
14.871 Section 8 Housing Choice Vouchers $154,915