Finding 512163 (2023-002)

Significant Deficiency Repeat Finding
Requirement
L
Questioned Costs
-
Year
2023
Accepted
2024-11-26

AI Summary

  • Issue: The final SF-428 and PHCP Progress Report were submitted late, violating grant agreement terms.
  • Impacted Requirements: Compliance with OMB guidelines and timely submission of required reports.
  • Recommended Follow-Up: Ensure future reports are submitted on time to avoid compliance issues.

Finding Text

Criteria - In accordance with the OMB Compliance Supplement and the grant agreement, the Organization is required to submit the PHCP Progress Report and SF-428 by the specified due date. Condition and Description - During our audit, we noted that the final SF-428 and PHCP Progress Report for the period ended December 31, 2023 was submitted after the due date. Questioned Costs - Unknown. Cause/Effect - The Organization failed to meet the reporting requirements outlined in the grant agreement and compliance supplement.

Corrective Action Plan

Due to administration issues, the Organization was unable to submit the reports in a timely manner. We will ensure that all the reports are timely submitted as per the grant requirements.

Categories

Reporting

Other Findings in this Audit

  • 512164 2023-003
    Material Weakness Repeat
  • 512165 2023-004
    Material Weakness Repeat
  • 512166 2023-005
    -
  • 512167 2023-002
    Significant Deficiency Repeat
  • 512168 2023-003
    Material Weakness Repeat
  • 512169 2023-004
    Material Weakness Repeat
  • 512170 2023-005
    -
  • 512171 2023-002
    Significant Deficiency Repeat
  • 512172 2023-003
    Material Weakness Repeat
  • 512173 2023-004
    Material Weakness Repeat
  • 512174 2023-005
    -
  • 512175 2023-002
    Significant Deficiency Repeat
  • 512176 2023-003
    Material Weakness Repeat
  • 512177 2023-004
    Material Weakness Repeat
  • 512178 2023-005
    -
  • 512179 2023-002
    Significant Deficiency Repeat
  • 512180 2023-003
    Material Weakness Repeat
  • 512181 2023-004
    Material Weakness Repeat
  • 512182 2023-005
    -
  • 1088605 2023-002
    Significant Deficiency Repeat
  • 1088606 2023-003
    Material Weakness Repeat
  • 1088607 2023-004
    Material Weakness Repeat
  • 1088608 2023-005
    -
  • 1088609 2023-002
    Significant Deficiency Repeat
  • 1088610 2023-003
    Material Weakness Repeat
  • 1088611 2023-004
    Material Weakness Repeat
  • 1088612 2023-005
    -
  • 1088613 2023-002
    Significant Deficiency Repeat
  • 1088614 2023-003
    Material Weakness Repeat
  • 1088615 2023-004
    Material Weakness Repeat
  • 1088616 2023-005
    -
  • 1088617 2023-002
    Significant Deficiency Repeat
  • 1088618 2023-003
    Material Weakness Repeat
  • 1088619 2023-004
    Material Weakness Repeat
  • 1088620 2023-005
    -
  • 1088621 2023-002
    Significant Deficiency Repeat
  • 1088622 2023-003
    Material Weakness Repeat
  • 1088623 2023-004
    Material Weakness Repeat
  • 1088624 2023-005
    -

Programs in Audit

ALN Program Name Expenditures
93.224 Community Health Centers $2.84M
93.527 Affordable Care Act (aca) Grants for New and Expanded Services Under the Health Center Program $171,164