Finding 504175 (2024-001)

Significant Deficiency
Requirement
I
Questioned Costs
-
Year
2024
Accepted
2024-10-30
Audit: 326621
Organization: Rocky Mountain Institute (CO)

AI Summary

  • Core Issue: The Organization failed to check the suspension and debarment status of a vendor before entering into a contract, violating federal regulations.
  • Impacted Requirements: Compliance with 2 CFR 180, which prohibits contracting with suspended or debarred parties.
  • Recommended Follow-up: Update policies to ensure the "Excluded Parties List" is reviewed before contracts are awarded and annually thereafter, with documentation included in contract files.

Finding Text

Finding: Suspension and Debarment Research and Development Cluster Department of State Assistance Listing Number 19.017 Environmental and Scientific Partnership and Programs Award Number: SAQMIP23GR0057 Award Year 2024 Criteria or Specific Requirement: Per 2 CFR 180, all non-federal entities are prohibited from contracting with or making sub-awards under covered transactions with parties that are suspended or debarred or otherwise excluded from or ineligible for participation in federal assistance programs or activities. Condition: Documentation to support compliance with the above requirement was not available in one instance in which the Organization did not check the suspension and debarment via the excluded parties listing (EPLS) prior to entering into the contract. Questioned Costs: None. Context: We tested a sample of 3 of 26 vendors to evaluate compliance with the applicable procurement requirements, including the review of the excluded party list, and noted the above issue related to the Climate Finance Access Network. A non-statistical sampling methodology was used to select the sample. Effect: By not verifying vendors against the excluded party list, the Organization risks contracting with and making payments to a contractor/vendor that has been suspended or debarred in a violation of federal regulations. Cause: The Organization did not have controls in place to perform the suspension and debarment check prior to entering into a covered transaction. Recommendation: We recommend that the Organization update its current policies and procedures to ensure that the "Excluded Parties List" be reviewed prior to awarding a provider contract, purchase order or contract extension, and on an annual basis thereafter. Performance of such reviews should be documented by including supporting documentation in the contract file.

Corrective Action Plan

RMI will leverage its current processes and policies to remedy the finding. RMI’s current signature authority process requires the Procurement Manager to approve the supplier before any contract is executed. The Procurement Manager or other procurement team member will complete a full vetting of the supplier before the Procurement Manager or procurement team member provides their sign off to move the contract towards execution. Vetting the supplier includes screening the supplier in ComplyAdvantage (a leading watchlist, AML/CFT, sanction list, and other risk screening database) and is a part of the documented procurement process and checklist. ComplyAdvantage screening meets the 2 CFR 180 requirements and checks the suspension and debarment via the excluded parties listing (EPLS). The Procurement Team is responsible for screening all active suppliers via Comply/Advantage on an annual basis. All screenings will be documented appropriately within the supplier record. The Procurement Team is responsible for completing an audit of all active suppliers as of the date of this action plan. Any active suppliers who have not been screened via ComplyAdvantage since November 2023 will need to be screened by the Procurement Team no later than 12/31/24. All findings will be documented appropriately within the supplier record.

Categories

Procurement, Suspension & Debarment

Other Findings in this Audit

  • 1080617 2024-001
    Significant Deficiency

Programs in Audit

ALN Program Name Expenditures
20.942 Thriving Communities Program $2.00M
81.122 Electricity Delivery and Energy Reliability, Research, Development and Analysis $222,250
98.001 Usaid Foreign Assistance for Programs Overseas $212,857
19.017 Environmental and Scientific Partnerships and Programs $193,572
47.084 Nsf Technology, Innovations and Partnerships $46,803
81.086 Conservation Research and Development $43,136