  • Core Issue: The Cooperative failed to fund the general operating reserve at the required 3% of member charges.
  • Impacted Requirements: This non-compliance violates HUD regulations regarding reserve fund maintenance.
  • Recommended Follow-Up: Ensure the Cooperative completes the necessary transfer to the reserve to maintain compliance.

Finding Text

Finding 2022-001 Criteria: The establishment and maintenance of a general operating reserve fund is a program requirement applicable to cooperative housing insured by HUD. Monthly payments of not less than 3% of the monthly charges to members are required. Upon accrual of an amount equal to 15% of the current annual charges to members, the rate may be reduced from 3% to 2% provided the total of the operating reserve does not fall below 15% of annual charges. Upon the operating reserve reaching 25% of the annual charges, payments into the reserve may be discontinued so long as the 25% level is maintained. If the level falls below 25%, monthly deposits of 3% of monthly charges shall commence until the 25% level is restored. Condition: The Cooperative did not adequately fund the general operating reserve at 3% of the member carrying charges. Questioned Costs: None. Context: The Cooperative did not adequately fund the general operating reserve. Effect: The Cooperative is out of compliance with the HUD regulatory agreement. Cause: The Cooperative?s deposits into the general operating reserve did not meet the 3% of the member carrying charges. Repeat Finding: N/A. Recommendation: We recommend that the Cooperative immediately transfer into the general operating reserve the amount needed to come back into compliance. Current Status: Resolved, the Cooperative made the transfer into the general operating reserve after year-end. Action Taken: The Cooperative will make the transfer. Views of Responsible Officials and Planned Corrective Actions: The Cooperative agrees with this finding and will adhere to the corrective action plan on page 27 in this audit report.

Corrective Action Plan

Housing and Urban Development Zvago Cooperative at St. Anthony Park respectfully submits the following corrective action plan for the year ended June 30, 2022. Westberg Eischens, PLLP 2630 1st Street South P.O. Box 362 Willmar, MN 56201 Audit Period: June 30, 2022 The findings from the June 30, 2022 schedule of findings and questioned costs are discussed below. The findings are numbered consistently with the numbers assigned in the schedule. Summary of audit results does not include findings and is not addressed. Finding 2022-001 Recommendation: We recommend that the Cooperative immediately transfer into the general operating reserve the amount needed to come back into compliance. Action Taken: The Cooperative will make the transfer. Planned Completion Date: September 30, 2022.

Categories

HUD Housing Programs

Other Findings in this Audit

  • 42537 2022-002
    Significant Deficiency
  • 618978 2022-001
    Significant Deficiency
  • 618979 2022-002
    Significant Deficiency

Programs in Audit

ALN Program Name Expenditures
14.126 Mortgage Insurance_cooperative Projects $11.15M