Reference Number 2023-001 Quality Assurance Program Verification Activities
(ALN 20.205)
Corrective Action:
Upon notification by TxDOT of the non-compliance on the 365 Tollway Project, the Authority took the following action:
1. Suspended work with consultant on November 10, 2023, and subsequently terminated their contract on December 21, 2023, for non-compliance with quality assurance requirements.
2. Enforced the contract with its Owner’s Independent Assurance Program (IAP) consultant to provide continuous monitoring of all technician certifications/accreditations for the life of the project.
3. Procured services to perform forensic investigation and evaluation of the work performed by the non-compliant technicians to confirm materials meet quality assurance standards.
Proposed Completion Date: The IAP is monitoring all technician certifications/accreditation and will continue monitoring for the life of the project. The forensic investigation and evaluation of the work performed by the non-compliant technicians will be completed by December 2024.
Name of contact person: Pilar Rodriguez, P.E., Executive Director