Finding 12468 (2022-001)

Significant Deficiency
Requirement
F
Questioned Costs
$1
Year
2022
Accepted
2023-03-27
Audit: 16944
Auditor: Auditor General

AI Summary

  • Core Issue: The District failed to include required clauses for the Davis-Bacon Act in a construction contract, leading to questioned costs of $73,820.
  • Impacted Requirements: Contracts over $2,000 must include prevailing wage rate clauses and require weekly certified payrolls to ensure compliance with federal wage standards.
  • Recommended Follow-Up: The District should improve procedures to ensure compliance with the Davis-Bacon Act and document the allowability of questioned costs to the U.S. Department of Education.

Finding Text

Finding: District controls did not always ensure compliance with the Davis-Bacon Act for Federally funded construction projects exceeding $2,000, resulting in questioned costs totaling $73,820. Criteria: The ESF ? Higher Education Emergency Relief Fund for the Improvement of Postsecondary Education Grant provides Federal funds for minor remodeling in a previously completed building for purposes associated with the coronavirus, such as minor building alterations to increase social distancing. Title 29, Section 5.5, Code of Federal Regulations (Davis-Bacon Act), requires the District to include prevailing wage rate clauses in any construction contract exceeding $2,000 that is financed either wholly or in part by Federal funds and ensure that contractors pay workers the prevailing wage rates established by the United States Department of Labor. This includes a requirement for the contractor to submit to the District weekly, for each week in which any contract work is performed, a copy of the payroll and a statement of compliance (certified payrolls). The United States Department of Labor established ?prevailing wages? by geographic area and interprets the Davis-Bacon Act to apply to construction, alteration, or repair of a public building or public work. Condition: The Board entered into a construction contract for building alterations to increase social distancing at the Flagler Technical Institute. During the 2021-22 fiscal year, the construction was completed and District ESF expenditures totaled $73,820 for the project. Our examination of the District records disclosed that the contract for the project did not contain clauses that required compliance with the Davis-Bacon Act. Also, according to District personnel, no one verified that the contractor submitted weekly certified payrolls demonstrating prevailing wage rates were paid. Cause: District personnel were not aware that the Davis-Bacon Act applied to the project and, therefore, did not include the appropriate wage rate clauses in the applicable procurement documents. In addition, according to District personnel, District procedures did not require them to verify that the contractor submitted weekly certified payrolls demonstrating prevailing wage rates were paid. Effect: Absent the required contract clauses and weekly certified payrolls, there is an increased risk that construction contractors paid with Federal moneys will not pay workers the prevailing wage rates established by the United States Department of Labor. Although we requested, the District did not provide the certified payrolls from the contractor demonstrating that the prevailing wage rates were paid for the project. Consequently, the District incurred questioned costs totaling $73,820. Recommendation: The District should enhance procedures to ensure compliance with all Davis-Bacon Act requirements. Such procedures should ensure that applicable Federally funded construction contracts contain the prevailing wage rate clauses and require submittal of weekly certified payrolls and that District personnel verify the payrolls were received. In addition, the District should document to the United States Department of Education (ED) the allowability of the questioned costs or contact the ED regarding necessary corrective action. District Response: The District is currently working with the contractor to obtain the required documents to be in compliance with the Davis-Bacon Act. In addition, the District will enhance its procedures to ensure that it complies with the Davis-Bacon Act.

Corrective Action Plan

The District will enhance its procedures to ensure that prevailing wage rate clauses are included in any construction contract exceeding $2,000 that is financed wholly or in part by Federal funds and that wage rates paid by contractors and subcontractors for Federally funded facility projects are directly compared to, and determined to be consistent with, the prevailing wage rates established for the geographic area by the United State Department of Labor.

Categories

Questioned Costs Procurement, Suspension & Debarment

Other Findings in this Audit

  • 588910 2022-001
    Significant Deficiency

Programs in Audit

ALN Program Name Expenditures
10.559 Summer Food Service Program for Children $6.56M
84.010 Title I Grants to Local Educational Agencies $2.98M
32.009 Emergency Connectivity Fund Program $1.04M
10.555 National School Lunch Program $586,264
84.367 Supporting Effective Instruction State Grants $479,024
84.287 Twenty-First Century Community Learning Centers $417,083
10.558 Child and Adult Care Food Program $380,495
17.259 Wia Youth Activities $294,640
84.424 Student Support and Academic Enrichment Program $224,637
84.002 Adult Education - Basic Grants to States $160,674
12.U01 Army Junior Reserve Officers Training Corps $134,772
93.575 Child Care and Development Block Grant $127,895
84.365 English Language Acquisition State Grants $93,358
84.063 Federal Pell Grant Program $83,597
84.196 Education for Homeless Children and Youth $45,369
84.048 Career and Technical Education -- Basic Grants to States $38,540
84.173 Special Education_preschool Grants $31,413
84.027 Special Education_grants to States $11,697
84.323 Special Education - State Personnel Development $11,614
84.425 Education Stabilization Fund $2,534