Finding 1241507 (2025-003)

Material Weakness Repeat Finding
Requirement
C
Questioned Costs
-
Year
2025
Accepted
2026-11-02

AI Summary

  • Core Issue: Internal controls over grant reimbursement requests are weak; approvals are not consistently done by the authorized Executive Director.
  • Impacted Requirements: Lack of independent review and segregation of duties increases risks of errors and noncompliance.
  • Recommended Follow-Up: Strengthen controls by ensuring all requests are reviewed and approved by the Executive Director, and maintain documentation of this process.

Finding Text

Federal Agency: U.S. Department of Health and Human Services Federal Program Name: Refugee and Entrant Assistance State/Replacement Designee Administered Programs (Refugee Support Services and Set Asides) Assistance Listing Number: 93.566 Federal Award Identification Number and Year: 2301MNRSS (2025) Pass-Through Agency: State of Minnesota, YMCA of the North, and CAPI USA Pass-Through Numbers: 258246, 258633, 258276 Award Period: January 1, 2025 – December 31, 2025 Type of Finding: - Material Weakness in Internal Control Over Compliance Criteria or Specific Requirement: Management has established controls requiring grant reimbursement requests to be reviewed and approved by the Executive Director prior to submission to the grantor. Approval should be performed by an authorized individual independent of the preparer to ensure adequate review and segregation of duties. Condition: Of the reimbursement requests selected for testing, multiple requests were approved by personnel other than the authorized Executive Director. In addition, the individual approving the reimbursement request was the same individual who prepared the request. As a result, controls requiring independent review and approval were not operating as designed, and adequate segregation of duties was not maintained over reimbursement request preparation and approval. Questioned Costs: None Context: Of the reimbursement requests selected for testing, multiple requests were approved by personnel other than the authorized Executive Director. As a result, the control requiring Executive Director review and approval was not operating as designed for those transactions. Cause: Established review and approval procedures for grant reimbursement requests were not consistently followed, and management had not implemented monitoring controls to ensure requests were reviewed by the authorized Executive Director prior to submission. Effect: The lack of independent review and approval increases the risk that errors, unsupported expenditures, inaccurate reimbursement amounts, or noncompliance with grant requirements may not be detected and corrected in a timely manner. Repeat Finding: No Recommendation: The Organization should strengthen its internal controls over grant reimbursement requests by ensuring all requests are reviewed and approved by the authorized Executive Director prior to submission to the grantor. Management should maintain documentation evidencing the review and approval and perform periodic monitoring to ensure compliance with established approval and segregation of duties requirements. Views of Responsible Officials: There is no disagreement with the audit finding. KOM acknowledges the finding. KOM has reported enhancements to month-end and year-end close processes and the engagement of a contract accounting firm beginning in August 2025 with expanded controller functions. KOM will establish a documented Schedule of Expenditures of Federal Awards (SEFA) preparation and review procedure. Federal expenditures will be reconciled to the general ledger, grant records, and supporting schedules; award and assistance listing information will be reviewed for completeness and accuracy. A qualified individual independent of preparation will review and document approval of the SEFA before it is provided to the external auditors.

Corrective Action Plan

Refugee and Entrant Assistance State/Replacement Designee Administered Programs Assistance Listing No. 93.566 Recommendation: The Organization should strengthen its internal controls over grant reimbursement requests by ensuring all requests are reviewed and approved by the authorized Executive Director prior to submission to the grantor. Management should maintain documentation evidencing the review and approval and perform periodic monitoring to ensure compliance with established approval and segregation of duties requirements. Explanation of disagreement with audit finding: There is no disagreement with the audit finding. Action taken in response to finding: Effective July 2026, KOM implemented an enhanced review and approval process for RPO reimbursement invoices. Each invoice is subject to review by two executives and requires two levels of approval. The Program Director and Executive Director are primarily responsible for the review and approval process. When the Executive Director is unavailable, the Finance Director provides the required review and approval. This process is intended to ensure appropriate oversight and documented authorization before reimbursement requests are submitted. Name of the contact person responsible for corrective action: Alice Buckner, Executive Director Planned completion date for corrective action plan: November 30,2026

Categories

Reporting Internal Control / Segregation of Duties Subrecipient Monitoring Cash Management Material Weakness

Other Findings in this Audit

  • 1241505 2025-003
    Material Weakness Repeat
  • 1241506 2025-003
    Material Weakness Repeat
  • 1241508 2025-004
    Material Weakness Repeat
  • 1241509 2025-004
    Material Weakness Repeat
  • 1241510 2025-004
    Material Weakness Repeat
  • 1241511 2025-005
    Material Weakness Repeat
  • 1241512 2025-005
    Material Weakness Repeat
  • 1241513 2025-005
    Material Weakness Repeat

Programs in Audit

ALN Program Name Expenditures
93.566 REFUGEE AND ENTRANT ASSISTANCE STATE/REPLACEMENT DESIGNEE ADMINISTERED PROGRAMS $219,238
10.561 STATE ADMINISTRATIVE MATCHING GRANTS FOR THE SUPPLEMENTAL NUTRITION ASSISTANCE PROGRAM $87,999
93.044 SPECIAL PROGRAMS FOR THE AGING, TITLE III, PART B, GRANTS FOR SUPPORTIVE SERVICES AND SENIOR CENTERS $49,088
20.205 HIGHWAY PLANNING AND CONSTRUCTION $30,094