Finding 1240407 (2025-004)

Material Weakness Repeat Finding
Requirement
B
Questioned Costs
-
Year
2025
Accepted
2026-10-13

AI Summary

  • Core Issue: Costs charged to federal awards were based on budgeted estimates rather than actual expenditures, leading to potential inaccuracies.
  • Impacted Requirements: Under 2 CFR Part 200, costs must be documented and based on actual benefits received, requiring regular updates and reconciliations.
  • Recommended Follow-Up: Management should create procedures for allocating costs based on actual data and perform periodic reconciliations to ensure compliance.

Finding Text

Statement of Condition During our testing of shared program and administrative expenses, we noted that NEW allocated costs to federal awards using budgeted percentages established at the beginning of the fiscal year. The budgeted allocation percentages were not subsequently reconciled to actual expenditures or actual program activity. As a result, amounts charged to federal awards were based on estimates rather than actual costs incurred for the benefit of each award. Criteria or Specific Requirement Under 2 CFR Part 200, costs charged to federal awards must be adequately documented, reasonable, allocable, and based on the relative benefits received by each program. Allocation methodologies should be supported by actual costs and updated periodically to reflect actual activity. Estimated allocations used for interim charging should be reconciled to actual costs in a timely manner. Questioned Costs Undetermined. Effect Costs charged to federal awards may not accurately reflect the actual benefit received by each program. Consequently, federal awards may have been overcharged or undercharged, resulting in potential questioned costs and noncompliance with federal cost principles. Cause Management did not have procedures in place to periodically compare budgeted allocations to actual costs and activity and to adjust charges to federal awards accordingly. Recommendation We recommend that management establish procedures to allocate costs based on actual expenditures and activity measures. Where estimates are used for interim reporting purposes, management should perform periodic reconciliations to actual costs and make any necessary adjustments to ensure federal programs are charged only for their allocable share of costs. For example, salary and related costs should be allocated based on contemporaneous time records kept by employees who are allocated to more than one program and/or federal grant source, while occupancy related costs should be allocated based on square footage utilized. Views of Responsible Officials and Corrective Action Plan Management agrees with the finding and will implement procedures to periodically reconcile allocation methodologies to actual expenditures and program activity.

Corrective Action Plan

Management agrees with the finding and will implement procedures to periodically reconcile allocation methodologies to actual expenditures and program activity.

Categories

Allowable Costs / Cost Principles

Other Findings in this Audit

  • 1240395 2025-001
    Material Weakness Repeat
  • 1240396 2025-002
    Material Weakness Repeat
  • 1240397 2025-003
    Material Weakness Repeat
  • 1240398 2025-004
    Material Weakness Repeat
  • 1240399 2025-005
    Material Weakness Repeat
  • 1240400 2025-006
    Material Weakness Repeat
  • 1240401 2025-001
    Material Weakness Repeat
  • 1240402 2025-003
    Material Weakness Repeat
  • 1240403 2025-004
    Material Weakness Repeat
  • 1240404 2025-001
    Material Weakness Repeat
  • 1240405 2025-002
    Material Weakness Repeat
  • 1240406 2025-003
    Material Weakness Repeat

Programs in Audit

ALN Program Name Expenditures
11.307 ECONOMIC ADJUSTMENT ASSISTANCE $834,519
17.285 REGISTERED APPRENTICESHIP $167,500
17.701 WOMEN IN APPRENTICESHIP AND NONTRADITIONAL OCCUPATIONS (€œWANTO€) TECHNICAL ASSISTANCE GRANT PROGRAM $160,642