Finding 1239071 (2025-005)

Material Weakness Repeat Finding
Requirement
HI
Questioned Costs
-
Year
2025
Accepted
2026-09-30
Audit: 413925
Organization: BLUE KREWE (LA)

AI Summary

  • Core Issue: Blue Krewe failed to complete the rooftop solar installation within the required Year 1 timeline set by the Cooperative Endeavor Agreement.
  • Impacted Requirements: This noncompliance could jeopardize the Organization's ability to meet federal award requirements and maintain good standing with the Environmental Protection Agency.
  • Recommended Follow-up: Management should secure written approval from the City for any revised project timelines and keep proper documentation of these changes.

Finding Text

2025-005 - Noncompliance with Required Project Deliverable Timeline – Significant Deficiency Federal Agency: Environmental Protection Agency Federal Program: Climate Pollution Reduction Grants (CPRG) Assistance Listing Number: 66.046 Pass-through Entity: City of New Orleans Award Identification Number: K25-486, BRASS No. 7241 Criteria The Cooperative Endeavor Agreement requires Blue Krewe to complete specified project deliverables within established performance periods. The Year 1 deliverables include installation of rooftop solar during the period October 11, 2024 through October 10, 2025. Condition Blue Krewe did not complete the required rooftop solar installation within the established Year 1 performance period. Management represented that it has remained in communication with the City regarding the status of the project and that no concerns have been raised by the City; however, written documentation from the City approving the delay was not available. Cause The rooftop solar installation was not completed within the timeframe established by the Cooperative Endeavor Agreement. Effect Failure to complete required project deliverables within established timelines results in noncompliance with the terms of the Cooperative Endeavor Agreement and could affect the Organization’s ability to demonstrate compliance with the requirements of the federal award. Recommendation Management should obtain written documentation from the City regarding revised project timelines or other modifications to required deliverables and maintain documentation supporting the City’s approval of changes to established performance requirements. Views of Responsible Official and Planned Corrective Actions Management acknowledges that the rooftop solar installation was not completed within the original Year 1 performance period. Management has been communicating with the City regarding the project and will continue to coordinate with the City regarding completion of the required deliverable and obtain and retain written documentation of any approved changes to the project timeline. Questioned Costs None.

Corrective Action Plan

Finding number: 2026-005 - Noncompliance with Required Project Deliverable Timeline Condition: Blue Krewe did not complete the required rooftop solar installation within the established Year 1 performance period. Management represented that it has remained in communication with the City regarding the status of the project and that no concerns have been raised by the City; however, written documentation from the City approving the delay was not available. Views of responsible official: Management acknowledges that the rooftop solar installation was not completed within the original Year 1 performance period. Management has been communicating with the City regarding the project and will continue to coordinate with the City regarding completion of the required deliverable and obtain and retain written documentation of any approved changes to the project timeline. Expected Completion date: November 30, 2026

Categories

Subrecipient Monitoring Period of Performance Significant Deficiency

Other Findings in this Audit

  • 1239070 2025-004
    Material Weakness Repeat

Programs in Audit

ALN Program Name Expenditures
66.046 CLIMATE POLLUTION REDUCTION GRANTS $1.06M