Finding 1227214 (2024-009)

Material Weakness Repeat Finding
Requirement
L
Questioned Costs
-
Year
2024
Accepted
2026-08-18

AI Summary

  • Core Issue: The Housing Authority submitted its audit late, repeating a previous finding.
  • Impacted Requirements: The audit and reporting package must be submitted within nine months post-audit period, per OMB guidelines.
  • Recommended Follow-up: Close financial records promptly and start the audit process earlier to meet submission deadlines.

Finding Text

2024-009 Late Audit Submission This is a repeat finding. The prior-year’s auditing finding number is 2023-009. Condition: The Housing Authority’s audit was not completed and the data collection form and reporting package were not submitted within nine months after the end of the audit period. Criteria: Section 200.512 Report Submission of the Office of Management and Budget’s Uniform Guidance states, “The audit must be completed and the data collection form described in paragraph (b) of this section and reporting package described in paragraph (c) of this section must be submitted within the earlier of 30 calendar days after receipt of the auditor’s report(s), or nine months after the end of the audit period. If the due date falls on a Saturday, Sunday, or Federal holiday, the reporting package is due the next business day.” Cause: The Housing Authority’s financial statements and records were not ready for audit in a timely fashion that allowed for a timely audit submission. Effect: Late submission of Single Audits can lead to a reduction of overall federal funding or effect the timing of funding. Recommendation: Ensure your books are closed in a timely fashion and schedule audit work to begin early enough so that your reporting package will be submitted on time. Views of Responsible Officials: See Corrective Action Plan.

Corrective Action Plan

2024-009 Late Audit Submission Material Weakness Recommendation: Ensure your books are closed in a timely fashion and schedule audit work to begin early enough so that your reporting package will be submitted on time. Action Taken: The Housing Authority agrees with this finding and will implement this recommendation within 120 days of this audit report.

Categories

Reporting

Other Findings in this Audit

  • 1227192 2024-001
    Material Weakness Repeat
  • 1227193 2024-002
    Material Weakness Repeat
  • 1227194 2024-003
    Material Weakness Repeat
  • 1227195 2024-004
    Material Weakness Repeat
  • 1227196 2024-005
    Material Weakness Repeat
  • 1227197 2024-006
    Material Weakness Repeat
  • 1227198 2024-007
    Material Weakness Repeat
  • 1227199 2024-008
    Material Weakness Repeat
  • 1227200 2024-009
    Material Weakness Repeat
  • 1227201 2024-010
    Material Weakness Repeat
  • 1227202 2024-011
    Material Weakness Repeat
  • 1227203 2024-012
    Material Weakness Repeat
  • 1227204 2024-013
    Material Weakness Repeat
  • 1227205 2024-014
    Material Weakness Repeat
  • 1227206 2024-001
    Material Weakness Repeat
  • 1227207 2024-002
    Material Weakness Repeat
  • 1227208 2024-003
    Material Weakness Repeat
  • 1227209 2024-004
    Material Weakness Repeat
  • 1227210 2024-005
    Material Weakness Repeat
  • 1227211 2024-006
    Material Weakness Repeat
  • 1227212 2024-007
    Material Weakness Repeat
  • 1227213 2024-008
    Material Weakness Repeat
  • 1227215 2024-010
    Material Weakness Repeat
  • 1227216 2024-011
    Material Weakness Repeat
  • 1227217 2024-012
    Material Weakness Repeat
  • 1227218 2024-013
    Material Weakness Repeat
  • 1227219 2024-014
    Material Weakness Repeat

Programs in Audit

ALN Program Name Expenditures
14.867 INDIAN HOUSING BLOCK GRANTS $360,217
14.862 INDIAN COMMUNITY DEVELOPMENT BLOCK GRANT PROGRAM $359,677