Finding 1226413 (2024-007)

Material Weakness Repeat Finding
Requirement
I
Questioned Costs
-
Year
2024
Accepted
2026-08-13
Audit: 409019
Auditor: UHY LLP

AI Summary

  • Core Issue: The Organization lacks a written procurement policy that complies with 2 CFR 200.318(a) of the Uniform Guidance.
  • Impacted Requirements: Failure to meet federal procurement standards may lead to violations of regulations.
  • Recommended Follow-Up: The Organization should create a compliant procurement policy to align with federal and state laws.

Finding Text

Federal Program/Award Identification: 10.525 Farm and Ranch Stress Assistance Network (FRSAN) Federal Award Project Number: 2020-70028-32729, 2023-70028-41283, and 2024-70028-43314 Federal Award Project Year: 2020 through 2026 Name of Federal Agency: United States Department of Agriculture Name of the Applicable Pass-Through Entity: National Institute of Food and Agriculture Criteria: The Organization is required to have a written procurement policy that reflects application of state, local, and tribal laws and regulations, as well as conforming to federal law and procurement standards per 2 CFR 200.318(a) of the Uniform Guidance. Condition: We noted that the Organization does not have a procurement policy that meets the requirements of 2 CFR 200.318(a) of the Uniform Guidance. Cause: The Organization was unaware of what was required in the written policy. Effect or Potential Effect: Violations of 2 CFR 200.318(a) of the Uniform Guidance could occur. Questioned Costs: None Context: UHY reviewed the Organization’s procurement policy and determined it was not sufficient to meet the requirements of 2 CFR 200.318(a) of the Uniform Guidance Recommendation: We recommend the Organization establish a written procurement policy that meets the standards of 2 CFR 200.318(a) of the Uniform Guidance. Views of Responsible Officials and Planned Correction Action: See “Management’s Response and Correction Active” plan section.

Corrective Action Plan

Planned Corrective Action: The Organization has a procurement policy within the Organization’s Internal Controls. The Organization has a procurement process within the Organization’s Operations Manual. However, they are missing key elements required in federal procurement. Both of these will be reviewed to ensure they align with CFR standards for federal procurement. Planned Implementation Date of Corrective Action: June 12, 2025 Name of Contact Person: Melinda Lequin, Executive Finance Director

Categories

Questioned Costs Procurement, Suspension & Debarment Subrecipient Monitoring

Other Findings in this Audit

  • 1226411 2024-005
    Material Weakness Repeat
  • 1226412 2024-006
    Material Weakness Repeat

Programs in Audit

ALN Program Name Expenditures
10.525 FARM AND RANCH STRESS ASSISTANCE NETWORK COMPETITIVE GRANTS PROGRAM $384,955
10.234 AMERICAN RESCUE PLAN TECHNICAL ASSISTANCE INVESTMENT PROGRAM $147,953
10.170 SPECIALTY CROP BLOCK GRANT PROGRAM - FARM BILL $36,353
10.500 COOPERATIVE EXTENSION SERVICE $21,057
10.181 PANDEMIC RELIEF ACTIVITIES: FARM AND FOOD WORKER RELIEF GRANT PROGRAM $20,255
10.215 SUSTAINABLE AGRICULTURE RESEARCH AND EDUCATION $16,415