Finding 1223623 (2025-002)

Material Weakness Repeat Finding
Requirement
B
Questioned Costs
-
Year
2025
Accepted
2026-07-14
Audit: 407121
Organization: Indiana Diaper Bank, Inc. (IN)
Auditor: PILE CPAS

AI Summary

  • Core Issue: The Organization lacked sufficient documentation for payroll expenses charged to federal programs, leading to noncompliance with federal regulations.
  • Impacted Requirements: Federal guidelines require accurate records of work performed and proper internal controls for payroll allocations, which were not met.
  • Recommended Follow-Up: Revise the timekeeping system and establish formal internal controls for time reporting to ensure compliance; recent improvements in August 2025 should be monitored for effectiveness.

Finding Text

Finding 2025-002 Insufficient Documentation of Personnel Expenses Type of Finding: Noncompliance and Material Weakness in Internal Control over Compliance Condition: The Organization charges a material amount of payroll-related costs to its major federal program. However, for 7 months of the year, it did not maintain sufficient documentation to support the level of effort charged to the award, as required by federal regulations. While staff members are required to complete timesheets, the format did not capture the level of detail needed to substantiate payroll allocations to federal programs. Additionally, there was no formal process for supervisory review and approval of these timesheets. Although no overcharges or double-dipping were identified, the lack of adequate documentation results in known and likely questioned costs due to noncompliance with documentation requirements. A new system was implemented in August 2025 which improved the deficiencies and compliance matters for the remainder of the year. Criteria: According to Uniform Guidance 2 CFR §200.430(g), the Organization's charges to federal awards for salaries and wages must be based on records that accurately reflect the work performed. These records must be supported by a system of internal control that provides reasonable assurance that the charges are accurate, allowable, and properly allocated. The records also must reasonably reflect the total activity for which the employee is compensated. The records also must support the distribution of the employee's salary or wages among specific activities or cost objectives if the employee works on more than one Federal award; a Federal award and non-Federal award; an indirect cost activity and a direct cost activity; two or more indirect activities allocated using different allocation bases; or an unallowable activity and a direct or indirect cost activity. Cause: This issue appears to stem from two primary causes: (1) the timesheet system in use was not designed to capture the information needed to support federal payroll charges, and (2) there is a lack of formal internal controls around timekeeping, including supervisory review and approval of reported time. Possible of Known Effect: As a result, a material amount of salary and payroll taxes charged to the federal program is not adequately supported in accordance with 2 CFR 200.430. This leads to both known and likely questioned costs. The absence of proper documentation increases the risk of misallocated expenses and undermines the Organization’s ability to demonstrate compliance with federal cost principles. Questioned Costs: Known questioned costs of $15,361 were identified. Repeat Finding: This finding is a repeat from the prior year. The previous finding was 2024-002. Recommendation: We recommend that the Organization revise its timekeeping system to ensure that staff members record time in a manner that clearly supports the allocation of payroll costs to federal programs. Additionally, we recommend the development and documentation of internal controls to oversee the time reporting process and ensure compliance with federal requirements. The changes implemented in August 2025 appear to address the issues identified in this finding. Views of Responsible Officials: The Organization started using features within Gusto beginning in August 2025 that capture employee name, pay period, hours worked by funding source, detailed notes (if applicable) and supervisory approval. The Organization trained all staff whose salaries are charged in whole or in part to grants on documentation and time allocation requirements. Monthly timesheets charged to grants are reviewed before submission for reimbursement. All timesheets require approval by a supervisor before payroll is processed and the final payroll requires two approvals by the CEO. Accounting Manager and/or the Development Manager. The Organization will conduct quarterly internal reviews to ensure compliance and adjust as needed.

Corrective Action Plan

Finding 2025-02 Insufficient Documentation of Personnel Expenses Condition: The Organization charges a material amount of payroll-related costs to its major federal program. However, for 7 months of the year, it did not maintain sufficient documentation to support the level of effort charged to the award, as required by federal regulations. While staff members are required to complete timesheets, the format did not capture the level of detail needed to substantiate payroll allocations to federal programs. Additionally, there was no formal process for supervisory review and approval of these timesheets. Although no overcharges or double-dipping were identified, the lack of adequate documentation results in known and likely questioned costs due to noncompliance with documentation requirements. A new system was implemented in August 2025 which improved the deficiencies and compliance matters for the remainder of the year. Corrective Actions Taken or Planned: The Organization started using features within Gusto beginning in August 2025 that capture employee name, pay period, hours worked by funding source, detailed notes (if applicable) and supervisory approval. The Organization trained all staff whose salaries are charged in whole or in part to grants on documentation and time allocation requirements. Monthly timesheets charged to grants are reviewed before submission for reimbursement. All timesheets require approval by a supervisor before payroll is processed and the final payroll requires two approvals by the CEO. Accounting Manager and/or the Development Manager. The Organization will conduct quarterly internal reviews to ensure compliance and adjust as needed.

Categories

Allowable Costs / Cost Principles Matching / Level of Effort / Earmarking

Other Findings in this Audit

  • 1223618 2025-001
    Material Weakness Repeat
  • 1223619 2025-002
    Material Weakness Repeat
  • 1223620 2025-003
    Material Weakness Repeat
  • 1223621 2025-004
    Material Weakness Repeat
  • 1223622 2025-001
    Material Weakness Repeat
  • 1223624 2025-003
    Material Weakness Repeat
  • 1223625 2025-004
    Material Weakness Repeat
  • 1223626 2025-001
    Material Weakness Repeat

Programs in Audit

ALN Program Name Expenditures
93.558 TEMPORARY ASSISTANCE FOR NEEDY FAMILIES $783,706
93.647 SOCIAL SERVICES RESEARCH AND DEMONSTRATION $87,629