Finding 1078181 (2020-009)

Significant Deficiency
Requirement
AB
Questioned Costs
$1
Year
2020
Accepted
2024-10-03

AI Summary

  • Core Issue: Significant deficiency in internal controls over compliance, leading to unsupported payroll disbursements.
  • Impacted Requirements: Failure to meet 2 CFR 200.303, which mandates effective internal controls for proper use of federal funds.
  • Recommended Follow-Up: Ensure ASRWSS adheres to internal control policies to support all expenditures and prevent unallowable costs.

Finding Text

Federal Agency: U.S. Department of Reclamation Federal Program Title: Fort Peck Reservation Rural Water System ALN Number: 15.516 Pass-Through Agency: N/A Pass-Through Number(s): N/A Award Number and Period: R03AV60749 March 31, 2019 R18AV00011 September 30, 2022 Statistically Valid Sample: No, and not intended to be a Statistically Valid Sample Type of Finding: Significant Deficiency in Internal Control Over Compliance and Other Noncompliance Criteria or Specific Requirement: Per 2 CFR 200.303 awardees must establish and maintain effective internal control to provide reasonable assurance that federal funds are being used appropriately. Condition/Context: During our testing of payroll and payroll-related expenditures, it was noted that of the 60 samples tested, 4 disbursements were not supported by an employee wage form on file. Questioned Costs: Known question costs of $581.22. Unable to determine likely questioned costs. Cause: ASRWSS policies and procedures were not consistently followed, and appropriate documentation was not maintained. Effect: Unallowable costs could be charged to the program. Lack of proper controls can result in misappropriation of ASRWSS resources. Repeat Finding: This is not a repeat finding. Recommendation: We recommend that ASRWSS follow their internal control policies and procedures to ensure that all expenditures are properly supported and charged to the correct grant. Views of Responsible Officials: There is no disagreement with the audit finding. Corrective Action Plan: See corrective action plan.

Categories

Questioned Costs Allowable Costs / Cost Principles

Other Findings in this Audit

  • 501732 2020-002
    Significant Deficiency Repeat
  • 501733 2020-003
    Material Weakness Repeat
  • 501734 2020-004
    Significant Deficiency Repeat
  • 501735 2020-005
    Material Weakness
  • 501736 2020-006
    Material Weakness Repeat
  • 501737 2020-007
    Material Weakness
  • 501738 2020-008
    Significant Deficiency
  • 501739 2020-009
    Significant Deficiency
  • 501740 2020-010
    Significant Deficiency Repeat
  • 501741 2020-011
    Significant Deficiency
  • 501742 2020-012
    Significant Deficiency Repeat
  • 501743 2020-013
    Significant Deficiency Repeat
  • 1078174 2020-002
    Significant Deficiency Repeat
  • 1078175 2020-003
    Material Weakness Repeat
  • 1078176 2020-004
    Significant Deficiency Repeat
  • 1078177 2020-005
    Material Weakness
  • 1078178 2020-006
    Material Weakness Repeat
  • 1078179 2020-007
    Material Weakness
  • 1078180 2020-008
    Significant Deficiency
  • 1078182 2020-010
    Significant Deficiency Repeat
  • 1078183 2020-011
    Significant Deficiency
  • 1078184 2020-012
    Significant Deficiency Repeat
  • 1078185 2020-013
    Significant Deficiency Repeat

Programs in Audit

ALN Program Name Expenditures
15.516 Fort Peck Reservation Rural Water System $12.18M
15.048 Bureau of Indian Affairs Facilities Operations and Maintenance $3.15M