Finding 1061716 (2024-005)

-
Requirement
B
Questioned Costs
-
Year
2024
Accepted
2024-08-28
Audit: 318038
Organization: Village of Kingsley (MI)
Auditor: Uhy LLP

AI Summary

  • Core Issue: The Village lacks updated written policies on allowable costs, conflict of interest, and procurement as required by the Uniform Grant Guidance.
  • Impacted Requirements: Compliance with §200.302(7) of the Uniform Guidance is necessary to ensure proper management of federal funds.
  • Recommended Follow-Up: The Village Council should promptly adopt the required written policies to prevent potential nonallowable costs in future federal programs.

Finding Text

2024-005 Written Policies Required by the Uniform Grant Guidance Program Title: Coronavirus State and Local Fiscal Recovery Funds Assistance Listing Number: 21.027 Federal Agency: U.S. Department of Treasury Federal Award Number: N/A Federal Award Year: Fiscal year 2024 Pass-Through Entities: Michigan Department of Environment, Great Lakes, and Energy (EGLE) and Grand Traverse County Type of Compliance: Immaterial noncompliance Criteria: The Uniform Guidance requires a non-federal entity that has expended federal awards for a grant awarded to have written policies pertaining to allowability of costs, payments, and compensation charged to federal programs (§200.302(7)). Condition: A formal written policy covering allowable costs, conflict of interest and procurement has not been updated in accordance with the Uniform Guidance. Cause: This condition appears to be the result of a time lag in identifying the requirement and developing a plan for compliance. Effect: The lack of written policies could result in costs or transactions that would be nonallowable for a federal program. Questioned Costs: None Perspective Information: The finding appears to be an isolated instance. No sampling was necessary to determine this finding. Identification of Repeat Findings: None Recommendations: The Village Council should, as soon as possible, adopt written policies, as required by Uniform Guidance, for allowable costs, conflict of interest and procurement. Views of Responsible Officials: The Village does not believe that there were any actual nonallowable costs or transactions because of the lack of written policies as required by Uniform Guidance. However, corrective action will be done whereby the written policies will be prepared and adopted for the future.

Categories

Procurement, Suspension & Debarment Allowable Costs / Cost Principles

Other Findings in this Audit

Programs in Audit

ALN Program Name Expenditures
21.027 Coronavirus State and Local Fiscal Recovery Funds $1.11M
20.205 Highway Planning and Construction $261,970