Finding 10526 (2022-002)

- Repeat Finding
Requirement
L
Questioned Costs
-
Year
2022
Accepted
2024-01-29

AI Summary

  • Core Issue: The Agency failed to file Forms SF-425 and SF-429 on time, missing the October 31, 2022 deadline.
  • Impacted Requirements: This delay resulted in non-compliance with grant reporting requirements.
  • Recommended Follow-Up: Ensure timely completion and submission of reports by the deadline to avoid repeat findings.

Finding Text

Criteria: These reports should be completed and filed in a timely manner by the Agency (by October 31, 2022 for the fiscal year ended June 30, 2022). Condition: It was noted that the Forms SF-425 and SF-429 were not filed in a timely manner. Cause: The former Chief Executive Officer/President left the Agency prior to the completion and submission of the forms and there was subsequently turnover in the accounting department. There were also delays with the new staff within the accounting department obtaining access to the necessary systems to submit the reports. Effect: The Agency was not in compliance with the grant’s reporting requirements. Questioned Cost Amount: None noted. Perspective Information: All of the reports required to be filed for the grant were tested and none were submitted timely. Repeat Finding: This is a repeat finding. Recommendation: We recommend that the reports be completed and submitted prior to or by the October 31st deadline. Views of Responsible Officials and Planned Corrective Action: The Agency agrees with this finding. See auditee’s corrective action plan.

Categories

Reporting

Other Findings in this Audit

  • 10513 2022-001
    Material Weakness
  • 10514 2022-002
    - Repeat
  • 10515 2022-003
    Material Weakness
  • 10516 2022-004
    Material Weakness
  • 10517 2022-001
    Material Weakness
  • 10518 2022-002
    - Repeat
  • 10519 2022-003
    Material Weakness
  • 10520 2022-004
    Material Weakness
  • 10521 2022-001
    Material Weakness
  • 10522 2022-002
    - Repeat
  • 10523 2022-003
    Material Weakness
  • 10524 2022-004
    Material Weakness
  • 10525 2022-001
    Material Weakness
  • 10527 2022-003
    Material Weakness
  • 10528 2022-004
    Material Weakness
  • 586955 2022-001
    Material Weakness
  • 586956 2022-002
    - Repeat
  • 586957 2022-003
    Material Weakness
  • 586958 2022-004
    Material Weakness
  • 586959 2022-001
    Material Weakness
  • 586960 2022-002
    - Repeat
  • 586961 2022-003
    Material Weakness
  • 586962 2022-004
    Material Weakness
  • 586963 2022-001
    Material Weakness
  • 586964 2022-002
    - Repeat
  • 586965 2022-003
    Material Weakness
  • 586966 2022-004
    Material Weakness
  • 586967 2022-001
    Material Weakness
  • 586968 2022-002
    - Repeat
  • 586969 2022-003
    Material Weakness
  • 586970 2022-004
    Material Weakness

Programs in Audit

ALN Program Name Expenditures
93.569 Community Services Block Grant $122,957
93.558 Temporary Assistance for Needy Families $114,713
93.600 Head Start $79,160
10.558 Child and Adult Care Food Program $1,288