Finding Number: 2023-005 Condition: Related to the Coronavirus State and Local Fiscal Recovery Funds (ALN 21.027), there was no evidence that reports were reviewed for completeness and accuracy prior to submission. Planned Corrective Action: The City hired a full-time Grants Manager in February 202...
Finding Number: 2023-005 Condition: Related to the Coronavirus State and Local Fiscal Recovery Funds (ALN 21.027), there was no evidence that reports were reviewed for completeness and accuracy prior to submission. Planned Corrective Action: The City hired a full-time Grants Manager in February 2024 to establish procedures to track grants that are awarded and expended by the City. New procedures will be developed to ensure that financial and performance reports for grants will be reviewed and approved by the Grants Manager prior to submission of the reports to the awarding entities. Documentation of this review will be retained with the grant documents. Contact person responsible for corrective action: Stacey Swanson, Grant & Special Revenue Manager Anticipated Completion Date: December 31, 2024
Finding Number: 2023-003 Condition: Related to the WaterSMART grant (ALN 15.507), controls in place were not adequate to ensure expenses were reported in the proper categories on the performance reports. Planned Corrective Action: The City hired a full-time Grants Manager in February 2024 to establ...
Finding Number: 2023-003 Condition: Related to the WaterSMART grant (ALN 15.507), controls in place were not adequate to ensure expenses were reported in the proper categories on the performance reports. Planned Corrective Action: The City hired a full-time Grants Manager in February 2024 to establish procedures to track grants that are awarded and expended by the City. New procedures will be developed to ensure that financial and performance reports for grants will be reviewed by the Grants Manager prior to submission of the reports to the awarding entities. Documentation of this review will be retained with the grant documents. Contact person responsible for corrective action: Stacey Swanson, Grant & Special Revenue Manager Anticipated Completion Date: December 31, 2024
Material Weakness, Inaccurate Schedule of Expenditures Of Federal Awards (The SEFA) Personnel Responsible for Corrective Action: Samantha Martin, County Administrator Anticipated Completion Date: 12/31/2024 Corrective Action Plan: The County agrees with the auditor’s recommendation to improve its ...
Material Weakness, Inaccurate Schedule of Expenditures Of Federal Awards (The SEFA) Personnel Responsible for Corrective Action: Samantha Martin, County Administrator Anticipated Completion Date: 12/31/2024 Corrective Action Plan: The County agrees with the auditor’s recommendation to improve its internal controls by implementing additional training and oversight of personnel to ensure the SEFA accurately reflects all federal expenditures for the fiscal year properly. The County is in the process of implementing an accounting software package with a corresponding month and year-end closing process to ensure balances are reconciled and reviewed.
Finding No. 2023-002 - Reporting; Significant Deficiency (HCV Cluster #14.871 and #14.879) Auditee's Response and Planned Corrective Action The Milton Housing Authority will develop better internal controls over the performance and documentation of SEMAP. To that end, a consultant has been contracte...
Finding No. 2023-002 - Reporting; Significant Deficiency (HCV Cluster #14.871 and #14.879) Auditee's Response and Planned Corrective Action The Milton Housing Authority will develop better internal controls over the performance and documentation of SEMAP. To that end, a consultant has been contracted and continues to train Employees. Staff is working with local HUD representatives for additional support. MHA will also consider outsourcing this to a reputable third party. Planned Implementation Date of Corrective Action: September 27, 2024 Person Responsible for Corrective Action: Earl Fay, Executive Director (617) 698-2169
Finding 2023-001 Material Weakness, Internal Control Over Compliance and Compliance, Reporting Personnel Responsible for Corrective Action: Adam Rogers Anticipated Completion Date: Already completed Corrective Action Plan: The County agrees with the auditor’s recommendation to improve its internal c...
Finding 2023-001 Material Weakness, Internal Control Over Compliance and Compliance, Reporting Personnel Responsible for Corrective Action: Adam Rogers Anticipated Completion Date: Already completed Corrective Action Plan: The County agrees with the auditor’s recommendation to improve its internal controls related to federal grant reporting requirements and has implemented a process that ensures federal expenditure accounting and reports are prepared by the Grants Analyst and then reviewed and approved by the Deputy Director of Finance or Director of Finance to provide oversight and detect and correct errors before reports are submitted.
Person responsible for corrective action plan: Anthony Madera, CFO Lummi Indian Business Council 2665 Kwina Road Bellingham, WA 98226 (360) 384-7181 Condition: 2 out of 40 samples were missing proof of insurance in the patient’s file, which is a requirement under the Department's eligibility polic...
Person responsible for corrective action plan: Anthony Madera, CFO Lummi Indian Business Council 2665 Kwina Road Bellingham, WA 98226 (360) 384-7181 Condition: 2 out of 40 samples were missing proof of insurance in the patient’s file, which is a requirement under the Department's eligibility policy. Solution: Implement a standardized process for verifying, documenting, and maintaining proof of required documents (e.g. proof of residency, insurance, etc.) in the patient's file during each visit. This will involve revising and implementing the new procedures manual to verify and document patient intake. The procedures manual will support appropriate communication from data collection to when information is uploaded into EPIC to verify if clients have insurance. Our training plan will incorporate these new methods of collecting data from the clients and outline regular internal auditing of patient files to assist the Tribal Assisters to properly verify documents and communicate with providers to assist clients in enrolling with insurance providers such as but not limited to Washington Apple Health (WAH). Corrective action plan will be in accordance with c CFR, Part 200, Subpart F, §200.511 Audit findings follow-up. Responsible: Kathryn Halverson, Health and Human Services CEO, Lummi Indian Business Council Anticipated completion date: 06/30/2025
Person responsible for corrective action plan: Anthony Madera, CFO Lummi Indian Business Council 2665 Kwina Road Bellingham, WA 98226 (360) 384-7181 Condition: During transactional testing, 11 of 16 individually important items (IIIs) were journal entries with no documented review and approval pro...
Person responsible for corrective action plan: Anthony Madera, CFO Lummi Indian Business Council 2665 Kwina Road Bellingham, WA 98226 (360) 384-7181 Condition: During transactional testing, 11 of 16 individually important items (IIIs) were journal entries with no documented review and approval process. Solution: With the guidance and authority outlined in the Department’s internal policies and in accordance with 2 CFR, Part 200, Subpart E, §200.405 Allocable costs, manual adjustments will be defined as reasonable and allocable as defined within existing governing statues, regulations, or terms and conditions of the award. Levels of delegation of staff administering these regulatory activities will utilize the appropriate credentials request cost adjustments and use prudent judgment to determine those costs are necessary and do not deviate from the Department’s established practices and policies. Final review of cost adjustment requests will be reviewed by Department’s OMB and once approved a signature of review and approval will be documented. Corrective action plan will be in accordance with c CFR, Part 200, Subpart F, §200.511 Audit findings follow-up. The Department entered into a professional agreement with Financial Service Advisors, LLC to assess current policies to update standards of management by identifying credentials and experience of senior finance staff who will oversee these activities. Revisions to the policies will provide the Department’s government an extensive manual that will be developed into a fiscal management training. Training will include but not be limited to reviewing procurement methods, fiscal review of ledger activity, and audit responsibility on a quarterly basis and reporting to tribal council. Responsible: Anthony Madera, Chief Financial Officer, Lummi Indian Business Council Anticipated completion date: 06/30/2025
Recommendation: We recommend that the Organization’s procurement policy is followed and that procurement procedures are documented, reviewed and approved. Explanation of disagreement with audit finding: There is no disagreement with the audit finding. Action planned in response to finding: We will...
Recommendation: We recommend that the Organization’s procurement policy is followed and that procurement procedures are documented, reviewed and approved. Explanation of disagreement with audit finding: There is no disagreement with the audit finding. Action planned in response to finding: We will review our current policies and procedures in these areas to determine if any changes should be implemented. We will ensure staff responsible for procurement of goods and services are familiar with applicable federal and state laws and policies for awarding and executing contracts. We are deeply committed to the continuous improvement of our purchasing policies and procedures to uphold the highest standards of transparency and accountability. In this regard, procurement policy will be updated to comply with the Uniform Guidance for federal awards. Furthermore, to strengthen our oversight of sole-source contracts awarded with program and non-program funds, we will introduce stringent measures requiring thorough documentation of the vendor’s or contractor’s qualifications. Name(s) of the contact person(s) responsible for corrective action: Department Head, Jan Warren/Amber Henderson (Compliance), Haydee Hill (CFO), Sharon Brown (CEO). Planned completion date for corrective action plan: 12/31/2024
Recommendation: We recommend that the Organization implement policies and procedures to ensure subrecipients are paid within 30 days of when the billing is received. If the request is believed to be improper, support for the delay in payment should be maintained. Explanation of disagreement with au...
Recommendation: We recommend that the Organization implement policies and procedures to ensure subrecipients are paid within 30 days of when the billing is received. If the request is believed to be improper, support for the delay in payment should be maintained. Explanation of disagreement with audit finding: There is no disagreement with the audit finding. Action planned in response to finding: We will review and update our policies and procedures for managing accounts payable. Furthermore, we will provide additional orientation and training sessions focused on disbursements for subrecipients involved in federal grant programs. We will improve the enforcement of policies and procedures by setting up a system to track the receipt and payment of bills. Additionally, we will implement a weekly review by the compliance team to ensure that payments are made on time and that accurate documentation is retained to support any delays in payment requests that are found to be inappropriate. Name(s) of the contact person(s) responsible for corrective action: Jan Warren/Amber Henderson (Compliance), Haydee Hill (CFO) Planned completion date for corrective action plan: 12/30/2024
All new client’s eligibility documents are reviewed by the Lead Case Manager to ensure that every required document for eligibility is in place. These clients were given a 30-day eligibility initially, allowing them time to collect required documents for complete eligibility. This was done for years...
All new client’s eligibility documents are reviewed by the Lead Case Manager to ensure that every required document for eligibility is in place. These clients were given a 30-day eligibility initially, allowing them time to collect required documents for complete eligibility. This was done for years, allowing clients to be seen by a medical provider quickly. This practice ended in 2023. 30-day eligibility is no longer allowed.
Finding 500284 (2023-007)
Significant Deficiency 2023
Type of Finding: Significant Deficiency in Internal Control over Compliance Federal Agency: U.S. Department of Defense Federal Program Name: Conservation and Rehabilitation of Natural Resources on Military Installations Assistance Listing Number: 12.005 Federal Award Identification Number and Year:...
Type of Finding: Significant Deficiency in Internal Control over Compliance Federal Agency: U.S. Department of Defense Federal Program Name: Conservation and Rehabilitation of Natural Resources on Military Installations Assistance Listing Number: 12.005 Federal Award Identification Number and Year: H79TI083313 - 2020 Award Period: September 28, 2020, through September 27, 2025 Criteria or specific requirement: 2 CFR 200.303(a) states that a non-federal entity must "Establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with Federal statutes, regulations, and the terms and conditions of the Federal award. These internal controls should be in compliance with guidance in “Standards for Internal Control in the Federal Government” issued by the Comptroller General of the United States or the “Internal Control Integrated Framework”, issued by the Committee of Sponsoring Organizations of the Treadway Commission (COSO)." Condition: During testing, 2 of the 60 samples selected had an individual approving their own timecard. Questioned costs: None. Context: A sample of 60 was made from a population of over 250 paychecks processed during the year with costs charged to the major program. Out of the 60 timecards that were sampled, there were two instances where the individual whose timecard was being reviewed also approved their own timecard. Cause: At the time of these payroll runs, the Organization did not have procedures in place to identify an appropriate approver for the Executive Director's timecards. Effect: Without appropriate segregation of duties around the approval of timecards, there is an increased risk of errors and fraud in the timekeeping and payroll process, which could result in inaccurate financial reporting and misappropriation of funds. Repeat Finding: No. Recommendation: CLA recommends that another individual with knowledge of the Executive Director's time and effort on the various programs approve his timecards. The Organization has already identified a member of the executive team to perform such functions and will implement the change going forward. Views of responsible officials: There is no disagreement with the audit finding. Action taken in response to finding: The organization has implemented a policy such that no employee can approve their own timecard. As noted above, the organization has identified an appropriate executive team member to approve the Executive Director’s timecard. Name(s) of the contact person(s) responsible for corrective action: Gary Slater Planned completion date for corrective action plan: 10/1/2024 If you have any questions regarding this plan, please call Gary Slater at 305-213-8829.
Finding 500282 (2023-005)
Significant Deficiency 2023
Type of Finding: Significant Deficiency in Compliance and Internal Control over Compliance Federal Agency: U.S. Department of Defense Federal Program Name: Conservation and Rehabilitation of Natural Resources on Military Installations Assistance Listing Number: 12.005 Federal Award Identification N...
Type of Finding: Significant Deficiency in Compliance and Internal Control over Compliance Federal Agency: U.S. Department of Defense Federal Program Name: Conservation and Rehabilitation of Natural Resources on Military Installations Assistance Listing Number: 12.005 Federal Award Identification Number and Year: H79TI083313 - 2020 Award Period: September 28, 2020, through September 27, 2025 Criteria or specific requirement: 2 CFR 200.302(a) on Financial management states that "... the other non-Federal entity's financial management systems, including records documenting compliance with Federal statutes, regulations, and the terms and conditions of the Federal award, must be sufficient to permit the preparation of reports required by general and program-specific terms and conditions; and the tracing of funds to a level of expenditures adequate to establish that such funds have been used according to the Federal statutes, regulations, and the terms and conditions of the Federal award". Condition: During testing, 2 of the 5 samples selected did not include sufficient documentation to agree all amounts requested for reimbursement for the month in question to the expenditures listed in the general ledger detail by program. Questioned costs: Unknown. Context: A sample of 5 monthly reimbursement requests were taken from a population of 13. Of the 5 sampled, two were insufficiently supported to agree the amounts requested for reimbursement for the month in question to the expenditures listed in the general ledger detail by program. Cause: The Organization was using a cumulative profit and loss to file monthly reimbursement requests (beginning of the year through the reimbursement month). In addition, profit and loss reports were not consistently saved at the time the reports were prepared for reimbursement for January and February 2023. Effect: The Organization is currently in noncompliance with federal regulations with regard to adequate documentation. Without adequate documentation in place to ensure costs are evidenced and reconcile to the expenditures documented in the underlying accounting information that is used to prepare the SEFA, the Organization could incorrectly charge expenditures to the federal program, or not request appropriate reimbursement that the Organization is entitled to under the terms of the grant. Repeat Finding: The finding is a repeat of a finding in the immediately prior year. Prior year finding number was 2022-005. Recommendation: Starting in March 2023, the Organization has already implemented a new process for the preparation of monthly reimbursement requests, including documentation retention. Point-in-time reports (i.e., profit and losses) are saved at the time of report preparation. This has enhanced clarity of costs attributable to each monthly period and reduces the chance that costs will be missed when requesting for reimbursement. Views of responsible officials: There is no disagreement with the audit finding. Action taken in response to finding: Previous corrective actions were completed in April 2024 upon receipt of our FY 2022 Audit from CLA. As noted above, we believe these corrective actions would have captured most, if not all, of the findings if they were in place for the entire FY23 period. That said we continue to review and strengthen our internal controls and training for admin staff for preparing reimbursement requests. Name(s) of the contact person(s) responsible for corrective action: Gary Slater Planned completion date for corrective action plan: 10/1/2024
Finding 500280 (2023-003)
Significant Deficiency 2023
Type of Finding: Significant Deficiency in Internal Control over Compliance Federal Agency: U.S. Department of Defense Federal Program Name: Conservation and Rehabilitation of Natural Resources on Military Installations Assistance Listing Number: 12.005 Federal Award Identification Number and Year:...
Type of Finding: Significant Deficiency in Internal Control over Compliance Federal Agency: U.S. Department of Defense Federal Program Name: Conservation and Rehabilitation of Natural Resources on Military Installations Assistance Listing Number: 12.005 Federal Award Identification Number and Year: H79TI083313 - 2020 Award Period: September 28, 2020, through September 27, 2025 Criteria or specific requirement: The Organization, as part of their stated controls, require that expenditures must be approved by the ED, CFO, or program directors / managers. In addition, § 200.303(a) requires the Organization to establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with Federal statutes, regulations, and the terms and conditions of the Federal award. Condition: During our testing, it was noted that 12 of 60 samples did not include sufficient records to substantiate approval of the disbursement. Questioned costs: None. Context: A sample of 60 was made from a population of over 250 disbursements charged to the major program. Of the 60 sampled costs, 12 did not have sufficient records to substantiate adequate approval. Cause: Approvals are not maintained for ACH transactions. Effect: Without adequate controls in place to ensure costs are reasonable and intended for the program charged, the Organization could incorrectly charge expenditures to the federal program, report fraudulent expenditures, or not request appropriate reimbursement that the Organization is entitled to under the terms of the grant. Repeat Finding: The finding is a repeat of a finding in the immediately prior year. Prior year finding number was 2022-003. Recommendation: CLA recommends that additional emphasis of documentary evidence of approvals be made, and such evidence should be obtained and retained by the Organization as proof of oversight of expenditure of federal funds. CLA would also recommend the use of an AP voucher, or similar, for each type of disbursement that leaves the Organization (check, ACH, EFT, credit card, etc.) to improve documentary evidence that costs are being reviewed and approved for appropriateness. Views of responsible officials: There is no disagreement with the audit finding. Action taken in response to finding: Previous corrective actions were completed in April 2024 upon receipt of our FY 2022 Audit from CLA. We believe these corrective actions would have captured most, if not all, of the findings if they were in place for the entire FY23 period. That said we have further reviewed and expanded our internal controls and training for all staff on documenting evidence of approvals, including obtaining and retaining necessary documentation and proof of expenditure oversight for federal funds to ensure there is adequate evidence that costs are being reviewed and approved for appropriateness. As noted above, we have added a procurement approval form and a standardized process for approval signature, quotes, sole source evidence and price analyses. We are also investigating an AP voucher process through our existing accounting software. Name(s) of the contact person(s) responsible for corrective action: Gary Slater Planned completion date for corrective action plan: 10/1/2024
Corrective Action: ABHS plans to optimize technology to improve the month-end closing process and allow for reconciliations to be performed on a consistent basis. Person Responsible: Alethea Velasquez, Chief Financial Officer, and CLA Estimated Completion Date: December 31, 2024
Corrective Action: ABHS plans to optimize technology to improve the month-end closing process and allow for reconciliations to be performed on a consistent basis. Person Responsible: Alethea Velasquez, Chief Financial Officer, and CLA Estimated Completion Date: December 31, 2024
View Audit 323061 Questioned Costs: $1
Over the past three years the hospital has been working hard to overcome a very hard financial turnaround. As a result, days cash on hand has been extremely low and there has been no way for the facility to make payroll, vendor payments, and debt payments, while maintaining a debt reserve. However, ...
Over the past three years the hospital has been working hard to overcome a very hard financial turnaround. As a result, days cash on hand has been extremely low and there has been no way for the facility to make payroll, vendor payments, and debt payments, while maintaining a debt reserve. However, over the past 12 months we have started to reap the reward of the hard work through operationally increasing revenue, reducing costs, and being more strategic on service lines. This will allow for us to hit the reserve amounts in 2025, while maintaining the cash flow needed for operations.
Finding 2023-001 –– During our current year audit, it was noted that one HCVP was not inspected during the year. In this instance, the Authority did not abate payments for this unit. It was also noted one instance of a unit failing inspection, and not passing within the 30 day window. However, the...
Finding 2023-001 –– During our current year audit, it was noted that one HCVP was not inspected during the year. In this instance, the Authority did not abate payments for this unit. It was also noted one instance of a unit failing inspection, and not passing within the 30 day window. However, the Authority never put the unit into abatement. Recommendation – We recommend that the Authority review their recertification process and their process for reporting the reinspection, and review the abatement process to ensure units are properly put into abatement when inspections are failed or incomplete. Action Taken – Chester County Housing Authority management agrees with the above recommendation and has instituted policies and procedures designed to address this finding. (Please see the list of approved policies and procedures.)
Finding No. 2023-003: Missing Procurement Documentation (Significant Deficiency) Person Responsible: Reginal Barner Date of Completion: 12/31/2024 Corrective Action Plan: The agency will assess the procurement process and implement internal controls where necessary.
Finding No. 2023-003: Missing Procurement Documentation (Significant Deficiency) Person Responsible: Reginal Barner Date of Completion: 12/31/2024 Corrective Action Plan: The agency will assess the procurement process and implement internal controls where necessary.
Finding No. 2023-002: Obligation Requirement for Capital Fund Program Drawdowns (Significant Deficiency Person Responsible: Reginal Barner Date of Completion: 12/31/2024 Corrective Action Plan: Our fee accountant will access the capital fund obligation and treasury process and implement corrective a...
Finding No. 2023-002: Obligation Requirement for Capital Fund Program Drawdowns (Significant Deficiency Person Responsible: Reginal Barner Date of Completion: 12/31/2024 Corrective Action Plan: Our fee accountant will access the capital fund obligation and treasury process and implement corrective actions, including adding internal controls and training.
Finding No. 2023-001: Fraudulent Payroll Activities Resulting in Theft (Material Weakness) Person Responsible: Reginal Barner Date of Completion: 12/31/2024 Corrective Action Plan: Our fee accountant and payroll consultant will access the payroll process and implement corrective actions, including a...
Finding No. 2023-001: Fraudulent Payroll Activities Resulting in Theft (Material Weakness) Person Responsible: Reginal Barner Date of Completion: 12/31/2024 Corrective Action Plan: Our fee accountant and payroll consultant will access the payroll process and implement corrective actions, including adding internal controls and training.
View Audit 323042 Questioned Costs: $1
Finding 2023-002 Grantor: Department of Health and Human Services Federal Program: Various Assistance Listing #: Various Title: Fringe Rate Analysis – Formula Error Award Year: Fiscal year 2023 1/1/2023 – 12/31/2023 Award Number: Various Management agrees with the recommendation. Ho...
Finding 2023-002 Grantor: Department of Health and Human Services Federal Program: Various Assistance Listing #: Various Title: Fringe Rate Analysis – Formula Error Award Year: Fiscal year 2023 1/1/2023 – 12/31/2023 Award Number: Various Management agrees with the recommendation. However, while there was an error in the underlying data used to evaluate the annual fringe rate, the federal government was not overcharged for fringe benefits. Corrective Action Plan and Anticipate Completion Date Management’s corrective action plan includes: • Management will ensure a more robust review of the underlying formulas. Responsible Person: Natasha Collins, Director of Research Accounting Completion Date: December 31, 2024
Management agrees and is planning on migrating from Little Green Light and moving solely to QuickBooks Online to track all revenue streams.
Management agrees and is planning on migrating from Little Green Light and moving solely to QuickBooks Online to track all revenue streams.
This has the potential to be a recurring item. Due to the size of the Organization’s administration team, total segregation of duties is not practical at this time. The Board will continue to be closely involved in financial reporting and will continue to provide oversight as practical in order to m...
This has the potential to be a recurring item. Due to the size of the Organization’s administration team, total segregation of duties is not practical at this time. The Board will continue to be closely involved in financial reporting and will continue to provide oversight as practical in order to mitigate the risk of misappropriation of assets
Finding Reference Number: 2023-2 Recommendation Management should establish internal controls and procedures to ensure that surplus cash is properly monitored and disbursed. Reporting views of responsible officials Auditee concurs with this finding. Auditee agrees with auditor recommendations. ...
Finding Reference Number: 2023-2 Recommendation Management should establish internal controls and procedures to ensure that surplus cash is properly monitored and disbursed. Reporting views of responsible officials Auditee concurs with this finding. Auditee agrees with auditor recommendations. Completion date or proposed completion date: December 31, 2024 Action(s) taken or planned on the finding Management agrees with the recommendation of the auditor and internal controls are being put in place to ensure that surplus cash is deposited into the residual receipts reserve prior to paying down intercompany balances.
View Audit 323017 Questioned Costs: $1
Finding 500167 (2023-003)
Significant Deficiency 2023
Recommendation: We recommend that the County review its internal controls and implement a procedure to ensure all reports required under the grant have a designated reviewer that is distinct from the individual responsible for preparing. We also recommend the County develop a procedure to ensure any...
Recommendation: We recommend that the County review its internal controls and implement a procedure to ensure all reports required under the grant have a designated reviewer that is distinct from the individual responsible for preparing. We also recommend the County develop a procedure to ensure any new grants awarded to the County have an internal control assessment performed to document the responsibilities of individuals involved in the grant’s management. Explanation of disagreement with audit finding: There is no disagreement with the audit finding. Action taken in response to finding: Finance Director is developing a procedure to ensure an internal control assessment is performed to document the grant management responsibilities of all grants. Name of the contact person responsible for corrective action: Darcy Smith, Finance Director Planned completion date for corrective action plan: October 31, 2024
2023-002 Coronavirus State and Local Fiscal Recovery Funds — Assistance Listing No. 21.027 Recommendation: Procurements should follow the required methods per Uniform Guidance and document the full procurement history. Procurement procedures should be designed, implemented, and written consistent w...
2023-002 Coronavirus State and Local Fiscal Recovery Funds — Assistance Listing No. 21.027 Recommendation: Procurements should follow the required methods per Uniform Guidance and document the full procurement history. Procurement procedures should be designed, implemented, and written consistent with Uniform Guidance. Personnel responsible for procurement should be trained on Uniform Guidance requirements and Centro Hispano's written procurement procedures. Action Taken: Centro Hispano drafted and approved an Accounting Policies and Procedures manual in September 2024 which conforms with Uniform Guidance requirements.
View Audit 322967 Questioned Costs: $1