Audit 408706

FY End
2025-12-31
Total Expended
$4.56M
Findings
1
Programs
11
Year: 2025 Accepted: 2026-08-07

Organization Exclusion Status:

Checking exclusion status...

Findings

ID Ref Severity Repeat Requirement
1226016 2025-001 Material Weakness Yes B

Contacts

Name Title Type
WTMVL67KNGU5 Melissa Sinclair Auditee
4797838172 Marc Lux Auditor
No contacts on file

Notes to SEFA

The accompanying schedule of expenditures of federal awards (the Schedule) includes the federal award activity of Sebastian County, Arkansas under programs of the federal government for the year ended December 31, 2025. The information in this Schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Because the Schedule presents only a selected portion of the operations of Sebastian County, Arkansas, it is not intended to and does not present the financial position, changes in net position, or cash flows, where applicable of Sebastian County, Arkansas.
No federal financial assistance has been provided to a subrecipient.

Finding Details

Management of the County is committed to taking steps to communicate with vendors concerning invoicing requirements to be included in initial contracts for CSLFRF projects. The County entered into a signed amendment by both parties as of 6/10/2024 to the original contract that for all future invoices provide a detailed explanation of sales tax amount to be reimbursed to the County and other ancillary costs above $50,000 concerning the AWIN Radio Towers Project. In addition, future invoices must contain detailed information specifying exactly the work which was performed. Management has further committed and is making attempts to obtain sufficient detailed documentation from Motorola Solutions on the AWIN Radio Towers Project. The County has continued to request additional detailed documentation multiple times to be provided by Motorola Solutions. A refund of sales taxes was issued to the County in October 2024 amounting to $340,693.48 relating to this project and Motorola. A letter from the Rose Law Firm was sent on 6/24/2025 to Motorola formally requesting documentation of detailed invoices for work Motorola performed. Motorola sent the requested invoice detailed support for the project for work performed as of 7/13/2023 on 11/20/2025. Motorola then sent the final invoice and detailed invoice support for the project on 5/1/2026. The County sent a letter to the U.S. Department of the Treasury on 6/17/2026 detailing the current status of the project which is the most recent correspondence on the project. As of the date of the audit report, the only remaining pending item on this Motorola Invoicing finding is the sales taxes to be paid on the Motorola project at completion which the County and Motorola are currently discussing to finalize.