Audit 388204

FY End
2025-06-30
Total Expended
$2.30M
Findings
2
Programs
2
Year: 2025 Accepted: 2026-02-19

Organization Exclusion Status:

Checking exclusion status...

Findings

ID Ref Severity Repeat Requirement
1174653 2025-001 Material Weakness Yes I
1174654 2025-002 Material Weakness Yes A

Programs

ALN Program Spent Major Findings
21.027 CORONAVIRUS STATE AND LOCAL FISCAL RECOVERY FUNDS $1.66M Yes 2
66.458 CLEAN WATER STATE REVOLVING FUND $638,235 Yes 0

Contacts

Name Title Type
E3UBJDLPKFK4 David Barnhouse Auditee
3073890411 Jason Lund Auditor
No contacts on file

Notes to SEFA

The accompanying Schedule of Expenditures of Federal Awards (SEFA) includes federal grant activity of the North Sweetwater Water and Sewer District, Wyoming (the District). The SEFA presents only a selected portion of the operations of the District, it is not intended to and does not present the financial position, changes in net position, or cash flows of the District.
Federal program expenditures included in the accompanying schedule are presented on the cash basis of accounting, the same as the District's financial statements. Expenditures are recorded when cash is paid. The information in the schedule is presented in accordance with requirements of Title 2 CFR Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance).
The District has not elected to utilize the 10 percent de minimis indirect cost rate.
The District did not pass any portion of federal awards to subrecipients.
The outstanding loans during the year are included in the SEFA. These loans were not fully drawn and accordingly had not entered the forgiveness/repayment phase at June 30, 2025. The District had following loan balances outstanding at June 30, 2025:

Finding Details

Finding 2025-001: Written Policies – Internal Control Finding – Significant Deficiency Assisted Listing Number: 21.027 Coronavirus State and Local Fiscal Recovery Funds Criteria: Uniform Guidance policies require 2 CFR Part 180 states written policies and procedures related to internal controls be written regarding SAM.gov contractor verification of debarment and suspension. Condition: North Sweetwater Water and Sewer District does not have a written policy implementing Uniform Guidance contractual and internal control procedures. Cause and Effect: While detail testing, we found no unallowed costs or vendors who were debarred or suspended with SAM.gov. However, without lack of written internal control policies the North Sweetwater Water and Sewer District could enter into transactions with debarred or suspended vendors. Repeat Finding: Repeat finding of 2024-001. Recommendation: We recommend that the North Sweetwater Water and Sewer District establish and maintain written internal control policies to contain all Uniform Guidance regulations, relating to SAMS.gov debarment and suspension and other federal contractual requirements. It is recommended that these policies and internal controls be reviewed in alignment with the Federal Award contractual agreements on a regular basis. Response: Please see the last page of this report for the North Sweetwater Water and Sewer District’s response to this finding.
Finding 2025-002: Approval of Expenditures– Internal Control Finding – Significant Deficiency Assisted Listing Number: 21.027 Coronavirus State and Local Fiscal Recovery Funds Criteria: Uniform Guidance policies require entities to establish and maintain effective internal control over federal awards that provides reasonable assurance that the entity is managing federal awards in compliance with federal statutes, regulations, and the terms and conditions of the federal award. Effective internal controls include documented approval processes for expenditures to ensure allowability, accuracy, and proper authorization. Condition: North Sweetwater Water and Sewer District did not consistently document evidence of supervisory review and approval for federal expenditures charged to the program. During testing, expenditures were processed and paid without documented approval by an authorized individual prior to disbursement. Cause: Unknown. Effect: Without a documented approval process, there is an increased risk that unallowable, inaccurate, or unauthorized expenditures could be charged to the federal program. Repeat Finding: N/A Recommendation: We recommend that management establish and enforce formal policies and procedures requiring documented supervisory approval of all federal expenditures prior to payment. Response: Please see the last page of this report for the North Sweetwater Water and Sewer District’s response to this finding.