Audit 371385

FY End
2024-06-30
Total Expended
$4.42M
Findings
10
Programs
12
Organization: Elementary School District 159 (IL)
Year: 2024 Accepted: 2025-10-28
Auditor: WIPFLI LLP

Organization Exclusion Status:

Checking exclusion status...

Findings

ID Ref Severity Repeat Requirement
1161478 2024-001 Material Weakness Yes L
1161479 2024-001 Material Weakness Yes L
1161480 2024-001 Material Weakness Yes L
1161481 2024-001 Material Weakness Yes L
1161482 2024-001 Material Weakness Yes L
1161483 2024-001 Material Weakness Yes L
1161484 2024-001 Material Weakness Yes L
1161485 2024-001 Material Weakness Yes L
1161486 2024-001 Material Weakness Yes L
1161487 2024-001 Material Weakness Yes L

Contacts

Name Title Type
WVK9KNN4CV53 Samantha Peterson Auditee
7087201300 Scott Duenser Auditor
No contacts on file

Notes to SEFA

See the Notes to the SEFA for chart/table instead
See the Notes to the SEFA for chart/table instead
See the Notes to the SEFA for chart/table instead

Finding Details

Criteria: As required by the Office of Management and Budget, auditees are required to submit a completed single audit to the Federal Audit Clearinghouse on or before the earlier of 30 days after the receipt of the auditor's report or nine months after the end of the audit period. Condition: The single audit report was not submitted timely. Questioned Costs: To be determined by grantor. Context: Due to delays in the audit process, the single audit was not filed timely. Effect: The District is at risk of jeopardizing the continued funding provided by the federal agencies. Cause: Delays in the audit process caused the late filing. Recommendation: We recommend the District implement policies and procedures related to the Uniform Guidance reporting requirements. Management's Response: The District will implement a process to track the submission time of the data collection form and audit package.