Finding 978831 (2023-002)

-
Requirement
ABL
Questioned Costs
$1
Year
2023
Accepted
2024-06-25
Audit: 309920
Organization: Semo Electric Cooperative (MO)

AI Summary

  • Core Issue: Inadequate documentation for materials charged to project work orders led to unsupported expenses in grant reporting.
  • Impacted Requirements: Effective controls for timely reconciliation between work order charges and contractor invoices were lacking.
  • Recommended Follow-Up: Implement procedures for timely reconciliations and maintain documentation to support material installations and project expenses.

Finding Text

ACTIVITIES ALLOWED/UNALLOWED; ALLOWABLE COST / COST PRINCIPLES; REPORTING Condition: Materials charged to project work orders and reported as installed, were not adequately supported by contractor invoices, and not identified in subsequent reconciliations tracking project activity for grant reporting. Criteria: Effective controls are required to ensure reported project materials and related expenses are installed, completed and adequately documented for approved project area. Controls should include timely reconciliation between work order charges and related contractor invoices supporting installation and materials used to support proper safeguards, disbursement, and reporting. Cause: Errors existed in the total materials charged to project work orders, which were not identified timely by the Cooperative’s current monitoring and control activity procedures. Effect: Controls did not exist to adequately monitor and report the material charges on project work orders used for grant reporting. As a result, errors may exist in reported project expenses. Questioned Cost and Context: Due to timing and volume of activity incurred on the grant project, material charges were evaluated in total for selected work orders as of December 31, 2023 and reconciled to contractor invoices over the same period. Testing identified $44,500 in material charges, of total project expenses of $1,129,351, not adequately supported and considered to be a questioned cost. Recommendation: Procedures should be implemented to ensure more timely reconciliation of material charges to work orders and reporting project grant expenses. Adequate documentation should be maintained to support controls in place and installation of materials at defined project area. Procedures should include additional oversight and timely reconciliations of project expenses completed and reported. Grantee’s Response: Management concurs. Large fiber installation project still in process at year-end. Subsequent reconciliations have been completed. Controls and other project processes have been improved to ensure more timely reconciliation of material charge-outs to the timing of the installation of material.

Categories

Questioned Costs Allowable Costs / Cost Principles Subrecipient Monitoring Reporting

Other Findings in this Audit

Programs in Audit

ALN Program Name Expenditures
21.029 Coronavirus Capital Projects Fund Program $197,808
21.027 Coronavirus State and Local Fiscal Recovery Funds $3,165