Regional School Unit 50 will take the following actions to address finding 2023-001: All Construction projects estimated at $2,000 or more will require a contract. All construction proposals and contracts in excess of $2,000 will be reviewed by the Business Manager to determine if the prevailing wage rate clause is needed. Each project will be reviewed along with the grant application to determine if there is a need to include a prevailing wage rate clause. No proposals of contracts being funded through federal assistance or with grants requiring the prevailing wage rate will be accepted by Regional School Unit 50 that do not include this clause. If determined that the Davis Bacon wage clause is required, the Business Manager will review to ensure that all language required by the Davis Bacon Wage Act is included.