Finding 600767 (2022-001)

Material Weakness
Requirement
N
Questioned Costs
-
Year
2022
Accepted
2023-02-01

AI Summary

  • Core Issue: The District spent $260,024 in federal grant funds without ensuring contracts included necessary wage rate compliance provisions.
  • Impacted Requirements: Contracts must comply with the Davis-Bacon Act and include weekly certified payroll reports to verify prevailing wages.
  • Recommended Follow-Up: Ensure all construction contracts over $2,000 include wage compliance provisions and establish a process to review payroll reports and report violations.

Finding Text

2 CFR 3474.1 provides that the Department of Education (DOE) adopts the Office of Management and Budget (OMB) Guidance in 2 CFR part 200. Thus, this section gives regulatory effect to the OMB guidance and supplements the guidance as needed for the DOE, except as otherwise noted in that section. Appendix II to 2 CFR part 200, Paragraph D states that all contracts made by the non-Federal entity under the Federal award must contain provisions covering the following: (D) Davis-Bacon Act, as amended (40 U.S.C. 3141-3148). When required by Federal program legislation, all prime construction contracts in excess of $2,000 awarded by non-Federal entities must include a provision for compliance with the Davis-Bacon Act (40 U.S.C. 3141-3144, and 3146-3148) as supplemented by Department of Labor regulations (29 CFR Part 5, ?Labor Standards Provisions Applicable to Contracts Covering Federally Financed and Assisted Construction?). In accordance with the statute, contractors must be required to pay wages to laborers and mechanics at a rate not less than the prevailing wages specified in a wage determination made by the Secretary of Labor. In addition, contractors must be required to pay wages not less than once a week. The non-Federal entity must place a copy of the current prevailing wage determination issued by the Department of Labor in each solicitation. The decision to award a contract or subcontract must be conditioned upon the acceptance of the wage determination. The non-Federal entity must report all suspected or reported violations to the Federal awarding agency. The contracts must also include a provision for compliance with the Copeland ?Anti-Kickback? Act (40 U.S.C. 3145), as supplemented by Department of Labor regulations (29 CFR Part 3, ?Contractors and Subcontractors on Public Building or Public Work Financed in Whole or in Part by Loans or Grants from the United States?). The Act provides that each contractor or subrecipient must be prohibited from inducing, by any means, any person employed in the construction, completion, or repair of public work, to give up any part of the compensation to which he or she is otherwise entitled. The non-Federal entity must report all suspected or reported violations to the Federal awarding agency. Lack of proper internal controls over Federal Grants management led to the District expending $260,024 of its Education Stabilization Fund (ESSER) American Rescue Plan (ARP), AL 84.425U, federal grant funds for replacement/renovation of HVAC systems and associated roof repair on District school buildings without the District?s contract with the vendor for these updates including a provision to ensure the contractor complied with Federal wage rate requirements. Additionally, the District did not obtain weekly certified payroll reports from the vendor to verify prevailing wages were paid. Without proper controls over wage rate requirements, there is an increased risk that the District and its contractors and subcontractors are not in compliance with applicable federal regulations. Noncompliance could result in federal funding being reduced or taken away, or other sanctions imposed by the federal grantor agency. The District should ensure contracts for construction in excess of $2,000 paid with federal grant monies contain a provision the contractor comply with the wage rate requirements and ensure certified payroll reports are provided weekly by the contractor. The District should review the certified payroll reports and report all suspected or reported violations to the Federal awarding agency.

Categories

Matching / Level of Effort / Earmarking Subrecipient Monitoring

Other Findings in this Audit

  • 24324 2022-001
    Material Weakness
  • 24325 2022-001
    Material Weakness
  • 600766 2022-001
    Material Weakness

Programs in Audit

ALN Program Name Expenditures
84.425 Education Stabilization Fund $309,657
84.010 Title I Grants to Local Educational Agencies $122,084
10.553 School Breakfast Program $81,664
84.027 Special Education_grants to States $38,425
84.367 Improving Teacher Quality State Grants $35,001
10.555 National School Lunch Program $31,169
84.424 Student Support and Academic Enrichment Program $10,205
84.173 Special Education_preschool Grants $2,889
10.649 Pandemic Ebt Administrative Costs $614