Finding 579188 (2022-008)

Material Weakness
Requirement
N
Questioned Costs
-
Year
2022
Accepted
2023-11-30
Audit: 4730
Organization: Coal Valley Water District (IL)

AI Summary

  • Core Issue: There are gaps in compliance controls related to the American Iron and Steel Act, specifically regarding contracts and documentation for sub-contractors.
  • Impacted Requirements: The program mandates compliance with the AIS, which was not fully met due to missing contracts and documentation for materials.
  • Recommended Follow-Up: Ensure all sub-contractors sign compliance contracts and verify material quantities before approving payments.

Finding Text

USDA Rural Development - Water and Waste Disposal Loans, Loan Guarantees, and Grants ALN 10.770 Federal Award Year 2022 - Material Weakness In Controls Over Compliance - Failure to obtain contracts for sub-contractors of the primary sub-contractor agreeing to American Iron and Steel Act (AIS) and other compliance requirements and failure to obtain documentation for quantities of AIS compliant materials for some iron and steel products. Criteria: This program requires compliance with the AIS. Condition - Some of the manufacturer certifications for material subject to the AIS did not show the quantites or place of delivery. In addition, sub-contractors of the primary sub-contractor, did not sign contracts assuring their agreement with these requirements. It does not appear that any of these sub-contractors provided any material. In fact, they were generally individual "contractual workers". Questioned costs - None. Repeat finding - No. Cause: Adequate documentation of AIS compliance, apparently, was not obtained prior to approving payments. Sub-sub-contracts and missing quantities were ignored. Recomendation: The District should insist that contracts are obtained from all sub-contractors (including workers the contractor or sub-contractor pay on a contractual basis). All contractors should agree to comply with AIS provisions of the original contract. Verification of delivery of quanties of Iron and Steel products should be obtained and reviewed prior to approving partial pay estimates.

Categories

Material Weakness Matching / Level of Effort / Earmarking Special Tests & Provisions

Other Findings in this Audit

  • 2744 2022-006
    Material Weakness
  • 2745 2022-007
    Material Weakness
  • 2746 2022-008
    Material Weakness
  • 579186 2022-006
    Material Weakness
  • 579187 2022-007
    Material Weakness

Programs in Audit

ALN Program Name Expenditures
10.770 Usda Water & Waste Disposal Loans, Loan Guarantees & Grants $4.26M