Finding 575557 (2024-002)

Material Weakness
Requirement
L
Questioned Costs
-
Year
2024
Accepted
2025-09-04
Audit: 365546
Organization: City of Grafton (ND)

AI Summary

  • Core Issue: The City failed to submit 2 out of 3 required SF-425 reports by the December 31 deadline.
  • Impacted Requirements: This non-compliance with Uniform Guidance affects the Airport Improvement Program reporting obligations.
  • Recommended Follow-Up: The City should establish procedures to ensure timely preparation and submission of all required reports.

Finding Text

Federal Program: Airport Improvement Program (AL 20.106) Reporting Criteria: Uniform Guidance deems SF-425 reports as direct and material. Through review of grant agreements, we noted that these are required to be submitted yearly by December 31 until the grant is completed. Condition: Through testing, we noted that the City had not prepared and submitted 2 of the 3 required SF- 425 reports by the December 31 deadline. Questioned Costs: None Context: In a population of 4, we selected 3 reports to test. We noted that 2 reports were not prepared and submitted by the due date. Cause: The City does not have the controls in place to ensure reports are being prepared and submitted. Effect: The City is in not in compliance with Uniform Guidance. Repeat Finding: No Recommendation: The City should implement procedures to ensure all required reports are prepared and submitted by their due dates. View of Responsible Officials and Planned Corrective Actions: The City agrees with the recommendation and will review its procedures.

Corrective Action Plan

Contact Person – City Administrator Corrective Action Plan – The City will implement procedures to ensure all required reports are prepared and submitted by their due dates. Completion Date – September 1, 2025

Categories

Reporting

Other Findings in this Audit

  • 1151999 2024-002
    Material Weakness

Programs in Audit

ALN Program Name Expenditures
20.106 Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and Covid-19 Airports Programs $882,632