Finding 573319 (2024-005)

Significant Deficiency
Requirement
M
Questioned Costs
-
Year
2024
Accepted
2025-08-12
Audit: 364120
Organization: City of Little Falls (MN)

AI Summary

  • Core Issue: The City lacks formal written controls for compliance with federal subrecipient monitoring requirements.
  • Impacted Requirements: This affects adherence to 2 CFR § 200.302(b) and the Uniform Guidance for federal awards.
  • Recommended Follow-Up: The City should draft and implement written policies for subrecipient monitoring to ensure compliance with federal regulations.

Finding Text

Finding 2024-005 Internal Controls Over Compliance for Subrecipient Monitoring Federal Program: 14.251 Economic Development Initiative, Community Project Funding, and Miscellaneous Grants Condition: The City does not have formally documented written controls to ensure compliance with the U.S. Office of Management and Budget’s (OMB) Uniform Administrative Requirement, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance), in regard to determining subrecipient monitoring. Criteria: 2 CFR § 200.302(b) requires the City to have written procedures related to managing subrecipient monitoring in accordance with 2 CFR 200 Subpart D – Subrecipient Monitoring. Cause: The City’s policies and procedures have not been formally drafted and updated in written form. Effect: The failure to have written policies and procedures resulted in the City’s noncompliance with the requirements of the Uniform Guidance. Context: This is a general requirement that pertains to many federal grants. This was not identified via sampling procedures. Questioned Costs: None identified. Recommendation: We recommend the City review the Electronic Code of Federal Regulations, particularly the sections referenced above, to obtain a better understanding of the related requirements under Uniform Guidance. Based on this understanding, we recommend the City adopt written policies and procedures pertaining to subrecipient monitoring for all applicable federal programs. Views of Responsible Officials and Planned Corrective Actions: Management agrees with our recommendation. See corresponding Corrective Action Plan.

Corrective Action Plan

Finding 2024-005 Internal Controls Over Compliance for Subrecipient Monitoring 1. Explanation of Disagreement with Audit Finding There is no disagreement with the audit finding. 2. Action Planned in Response to Finding The City will adopt the referenced policies in order to comply with Uniform Guidance. 3. Official Responsible Ms. Sony Lubrecht, Finance Director, is the official responsible for ensuring corrective action. 4. Planned Completion Date December 31, 2025. 5. Plan to Monitor Completion The City Council will be monitoring this Corrective Plan.

Categories

Subrecipient Monitoring Allowable Costs / Cost Principles

Other Findings in this Audit

  • 1149761 2024-005
    Significant Deficiency

Programs in Audit

ALN Program Name Expenditures
14.251 Economic Development Initiative, Community Project Funding, and Miscellaneous Grants $1.50M
20.106 Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and Covid-19 Airports Programs $360,659
15.904 Historic Preservation Fund Grants-in-Aid $464