Corrective Action Plan
For the year ended June 30, 2024
2024-001 Compliance Over Reporting
Response and Corrective Action Plan: The June 30, 2024 audit package were delayed
due to several factors including a change in finance leadership whereby the new
leadership was not part of the 2023-2024 accounting oversight. Additionally, during the
fiscal year several system transitions occurred including a change in accounting
software, change in accounts payable approval software, change in banks and
investment accounts. Finally, without permanent accounting leadership, proper
account reconciliations had been neglected are prepared well after the fiscal year end.
A full time, permanent CFO was hired July 1, 2024 and has been working with the
existing finance team to maintain proper accounting records including an updated
general ledger reconciled to sub ledgers for all balance sheet accounts. It is anticipated
that the audit package for fiscal year end June 30, 2025 will be completed timely.
Anticipated Completion Date: The process to improve timely audit package report
has been ongoing throughout fiscal year 2025 and the 2025 audit is projected to be
completed by December31, 2025.
Responsible party: Brent Willman, CFO and Lanny Suwarno, Controller