Finding 560496 (2024-001)

Significant Deficiency Repeat Finding
Requirement
I
Questioned Costs
-
Year
2024
Accepted
2025-05-15

AI Summary

  • Core Issue: The District lacks adequate internal controls for procurement procedures, failing to comply with federal regulations.
  • Impacted Requirements: Non-compliance with U.S. Code of Federal Regulations Title 2, Part 200, affecting vendor contract management and review processes.
  • Recommended Follow-Up: Implement controls to ensure proper vendor reviews and update procurement policies to align with federal guidance.

Finding Text

2024-001 Procurement Policies and Procedures Federal Agency: U.S. Department of Treasury Federal Program Name: COVID-19 Coronavirus State and Local Fiscal Recovery Funds Assistance Listing Number: 21.027 Federal Award Identification Number and Year: ISA-ARPA-ADWR-123022-01 - 2023 Pass-Through Agency: State of Arizona Governor’s Office Pass-Through Number(s): ERMT-20-002 Award Period: January 1, 2023 through January 1, 2026 Type of Finding: Significant Deficiency in Internal Control over Compliance Criteria or specific requirement: Under the U.S. Code of Federal Regulations Title 2, Part 200, Uniform Administrative requires certain elements to be part of the District’s procurement standards. The general procurement standards require the District to have and use documented procurement procedures that conform to the procurement standards identified in § 200.317 through 200.327 of the Uniform Guidance. The details of this requirements can be found in Title 2, Part 200, CFR Section 318(a). Condition: During our testing, we noted the District did not have adequate internal controls designed to ensure procurement procedures that conform to Uniform Guidance were followed, or designed to ensure vendors were not suspended or debarred. Questioned costs: None Context: During our testing, it was noted that the District was not following their federal procurement policy #2023-05 to ensure compliance with CFR, Subtitle A Chapter II, Part 200, Subparts D and E when entering into vendor contracts. Also noted the District was not reviewing vendors prior to entering into a contract to ensure the vendor was not on the suspended or debarred vendor list maintained by the General Services Administration. Cause: The District does not have effective internal controls in place to ensure compliance with the Uniform Guidance procurement rules and procedures. Effect: The lack of internal controls over the provisions of procurement, suspension, and debarment compliance requirements provides an opportunity for noncompliance. Repeat Finding: Repeat of prior year finding 2023-001. Recommendation: We recommend the District design controls to ensure an adequate review process is in place to review potential contractors to determine compliance with the Uniform Guidance procurement rules and procedures. Views of responsible officials and planned corrective actions: Management concurs with the finding, and as reported in the corrective action plan, District policies will be updated and approved to conform to federal guidance.

Corrective Action Plan

U.S. Department of Treasury Central Arizona Irrigation & Drainage District respectfully submits the following corrective action plan for the year ended December 31, 2024. Audit period: January 1, 2024 - December 31, 2024 The findings from the schedule of findings and questioned costs are discussed below. The findings are numbered consistently with the numbers assigned in the schedule. FINDINGS-FINANCIAL STATEMENT AUDIT Our audit did not disclose any matters required to be reported in accordance with Government Auditing Standards. FINDINGS-FEDERAL AWARD PROGRAMS AUDITS U.S. DEPARTMENT OF TREASURY 2024-001 21.027 COVID-19 Coronavirus State and Local Fiscal Recovery Funds -Assistance Listing No. Recommendation: We recommend the District design controls to ensure an adequate review process is in place to ensure potential contractors are in compliance with the Uniform Guidance procurement rules and procedures. Explanation of disagreement with audit finding: There is no disagreement with the audit finding. Action taken in response to finding: The District's policies will be updated and approved if needed to confirm to federal guidance. Name(s) of the contact person(s) responsible for corrective action: Ron McEachern, General Manager, Derek McEachern, Deputy General Manager, or Delia Stoor, Accounting Manager. Planned completion date for corrective action plan: September 30, 2025. If the U.S. Department of Treasury has questions regarding this plan, please call Ron McEachern, General Manager, Derek McEachern, Deputy General Manager, ot Delia Stoor, Accoutning Manager at 520-466-7336.

Categories

Procurement, Suspension & Debarment

Other Findings in this Audit

  • 1136938 2024-001
    Significant Deficiency Repeat

Programs in Audit

ALN Program Name Expenditures
21.027 Coronavirus State and Local Fiscal Recovery Funds $1.82M
15.530 Water Conservation Field Services (wcfs) $38,831