The Davis-Bacon Act requires contractors and subcontractors working on federally funded or assisted construction projects to pay their laborers and mechanics prevailing wages and benefits, as determined by the Department of Labor. For school districts involved in such projects, ensuring compliance with the Davis-Bacon Act involves several key procedures:
1. Project Planning and Contracting: Prevailing Wage Determination: Obtain the prevailing wage rates from the Department of Labor for the locality where the project is to be performed. Contract Clauses: Include Davis-Bacon Act clauses in all construction contracts and subcontracts. This should specify the obligation to pay prevailing wages, submit certified payrolls, and allow for site inspections.
2. Pre-Construction Conference: Training and Guidance: Conduct pre-construction meetings with contractors and subcontractors to explain Davis-Bacon Act requirements, including prevailing wage rates, payroll reporting, and compliance procedures.
3. Wage Decision Posting: On-Site Posting: Ensure that the applicable wage determination and the Department of Labor's "Employee Rights Under the Davis-Bacon Act" poster are posted at the job site in a conspicuous place accessible to all workers.
4. Certified Payrolls: Submission Requirements: Require contractors and subcontractors to submit weekly certified payrolls using Form WH-347 or an equivalent form. The payroll must include details on hours worked, wage rates, fringe benefits, and deductions.
5. Review and Verification: Payroll Review: Regularly review submitted certified payrolls to verify compliance with wage determinations. Cross-check the reported wage rates and classifications with the prevailing wage rates. Worker Interviews: Conduct periodic on-site interviews with workers to verify that they are receiving the appropriate wages and benefits as reported on the certified payrolls.
6. Enforcement Actions: Non-Compliance Follow-Up: If discrepancies or non-compliance are identified, promptly address these issues with the contractor. Require corrective actions and ensure that any underpayments are rectified. Withholding Payments: Withhold contract payments as necessary to ensure compliance or to cover any underpayments until the contractor corrects the violations.
7. Documentation and Recordkeeping: Maintan Records: Keep detailed records of all wage determinations, certified payrolls, enforcement actions, and communications related to compliance with the Davis-Bacon Act. Retain these records for at least three years after project completion.
8. Audit and Oversight: Internal Audits: Conduct internal audits and oversight activities to ensure ongoing compliance. This may involve random checks and reviews by the district's compliance officers or external auditors.
9. Reporting to Funding Agencies: Regular Reports: Submit required reports to the relevant federal or state agencies overseeing the project, demonstrating compliance with the Davis-Bacon Act requirements.
Cordell Public Schools has implemented the above procedures in January 2024, we can ensure compliance with the Davis-Bacon Act, thereby protecting workers' rights and avoiding potential legal and financial penalties.
The carryover from a fiscal year project will be reevaluated. The project still fell under our corrective action plan but was not a new project that was in line with the actions listed above. We closed out the fiscal year, opened the new year to continue the project, therefore we still were not in compliance with the Davis-Bacon Act or our procedures. However, all future projects have been in compliance. In the next overlapping project, we will consult our auditors and find the best way to leave open funds to finish the project, but not start over in a new fiscal year.