Finding 523675 (2024-002)

- Repeat Finding
Requirement
I
Questioned Costs
-
Year
2024
Accepted
2025-02-19

AI Summary

  • Core Issue: The Authority lacks documented procurement procedures, which is a repeat finding from the previous year.
  • Impacted Requirements: This affects compliance with federal procurement standards outlined in 2 CFR 200.318 and 2 CFR 200.320.
  • Recommended Follow-up: The Authority should prioritize creating and approving documented procurement procedures to ensure compliance moving forward.

Finding Text

Finding Reference: 2024-002 – Procurement Policies and Procedures Federal Agency: U.S Department of Agriculture Federal Program: Water and Waste Disposal System for Rural Communities - ALN# 10.760 Compliance Requirement: Procurement, suspension, and debarment Criteria: The Uniform Guidance requires that non-federal entities must have and use documented procedures consistent with laws and regulations and the standards for the acquisition of property or services under a federal award or subaward in accordance with 2 CFR 200.318. Additionally, the non-federal entity is required to follow formal procurement methods when the value of the procurement property or service under a federal financial assistance award exceeds the simplified acquisition threshold in accordance with 2 CFR 200.320. Condition: The Authority does not have any documented procurement procedures. However, during our testing of compliance with procurement guidelines, no further deviations from federal guidelines were noted. This is a repeat finding finding from the prior year. Cause and Effect: The Authority was unacquainted with general procurement standards of the Uniform Grant Guidance. Without documented procurement procedures, it is difficult for the Authority to ensure compliance with relevant compliance requirements. Questioned Cost: None Recommendation: The Authority should establish documented procedures related to federal procurement. Views of Responsible Officials: The federal project that has been in the works for multiple years, and, as a result, the Authority determined established procurement procedures would not be written and approved. The Authority did not make this decision in haste. The Authority met compliance guidelines for the procedures of items during the project. What we lack is an approved written document, which at this time is something we do not have the resources to undertake.

Corrective Action Plan

Corrective Action Planned: The federal project that has been in the works for multiple years, and, as a result, the Authority determined established procurement procedures would not be written and approved. The Authority did not make this decision in haste. The Authority met compliance guidelines for the procedures of items during the project. What we lack is an approved written document, which at this time is something we do not have the resources to undertake. Anticipated Completion Date: Ongoing Contact Person Responsible: Jennie Weary, Treasurer/Secretary

Categories

Procurement, Suspension & Debarment

Other Findings in this Audit

Programs in Audit

ALN Program Name Expenditures
10.760 Water and Waste Disposal Systems for Rural Communities $1.02M