Finding 519763 (2024-005)

Significant Deficiency Repeat Finding
Requirement
N
Questioned Costs
-
Year
2024
Accepted
2025-01-20
Audit: 338885
Auditor: Wipfli LLP

AI Summary

  • Core Issue: The District failed to meet financial covenants required for the Community Facilities Loans and Grants program.
  • Impacted Requirements: Noncompliance with financial covenants as outlined in the Hospital Revenue Bonds Series A loan documents.
  • Recommended Follow-Up: Management should implement a plan to achieve compliance with financial covenants and maintain communication with the USDA regarding improvements.

Finding Text

Repeat Finding: Yes Program Name: Community Facilities Loans and Grants Assistance Listing Number: 10.766 Federal Agency: U.S. Department of Agriculture Questioned Costs: N/A Type of Finding: Noncompliance, Significant Deficiency Compliance Requirement: Special Tests and Provisions Condition: The District did not meet its financial covenants required under the program during the year, and we, as the auditors, were unable to properly calculate the required financial covenants because of potential missing or misstated financial statement information due to the adverse opinion on the 2022 financial statements and related disclaimer of opinion included in our accompanying 2023 Independent Auditor's Report. Criteria The District is required to meet certain financial covenants as described in Article VIII of the Hospital Revenue Bonds Series A loan documents dated October 25, 2012. Cause: The District has had significant financial challenges and turnover within its finance department. Effect: The District was not in compliance with the program. Recommendation: We recommend that management put a plan in place to become compliant with the financial covenants of the debt. Review of Responsible Officials: Managemet acknowledges they were not in compliance with the financial covenants of the bond. Management has been in contact USDA to keep them informed on the situation and has put plans into place to improve the financial position of the District.

Corrective Action Plan

Finding # 2024-005 Condition: The District did not meet its financial covenants required under the program during the year, and we, as the auditors, were unable to properly calculate the required financial covenants because of potential missing or misstated financial statement information due to the adverse opinion on the 2022 financial statements and related disclaimer of opinion included in our accompanying 2023 Independent Auditor's Report Response: The hospital has financial covenants including: Maintaining 35 days cash on hand. We are currently at 26 Days Cash on Hand. The hospital has been as low as 6 Days Cash on Hand. To increase our Cash on Hand, we have brought all Revenue Cycle efforts in house, trained new staff, formed cross functional teams with the clinical documentation staff, set goals and work weekly with our teams to gently resolve challenges and move forward. These efforts have rewarded the hospital with increased Days Cash on Hand and improved quality processes in Revenue Cycle. One covenant requires that we maintain strong internal controls. Since the new administration have begun, each month, new internal controls are being established throughout the hospital, Finance department, Materials Management and the Revenue Cycle. On covenant requires a positive bottom line. The hospital has been losing money primarily due to the change in administration, lack of routine processes, recruitment challenges, lack of accuracy in our accounting and revenue cycle. Throughout the hospital and RHC’s, improvement teams are working to both improve quality processes, reduce costs, establish a culture to allow recruitment and improve our bottom line. The hospital has been transparent with the agency and our Board of Directors throughout our change process. More work continues. Responsible Party: Meagan Weber, CEO, Brent Peirick, COO, Carolyn Davies, CFO Estimated Completion Date: 12/31/2026

Categories

Special Tests & Provisions Significant Deficiency Matching / Level of Effort / Earmarking

Other Findings in this Audit

  • 519762 2024-004
    Significant Deficiency Repeat
  • 519764 2024-005
    Significant Deficiency Repeat
  • 519765 2024-004
    Significant Deficiency Repeat
  • 1096204 2024-004
    Significant Deficiency Repeat
  • 1096205 2024-005
    Significant Deficiency Repeat
  • 1096206 2024-005
    Significant Deficiency Repeat
  • 1096207 2024-004
    Significant Deficiency Repeat

Programs in Audit

ALN Program Name Expenditures
10.766 Community Facilities Loans and Grants $6.90M
93.912 Rural Health Care Services Outreach, Rural Health Network Development and Small Health Care Provider Quality Improvement $31,853
93.301 Small Rural Hospital Improvement Grant Program $10,933