Finding 51300 (2022-002)

Significant Deficiency
Requirement
N
Questioned Costs
-
Year
2022
Accepted
2023-09-24
Audit: 41231
Organization: Capitol Commons (LA)
Auditor: Wharton CPA LLC

AI Summary

  • Core Issue: Management did not obtain required bids for services over $10,000.
  • Impacted Requirements: HUD guidelines mandate soliciting bids from at least three contractors for such contracts.
  • Recommended Follow-Up: Ensure compliance with HUD procurement rules to avoid future violations.

Finding Text

2022-2 No Bids Provided Condition: Management failed to provide bids for procured services that exceeded $10,000 or more. Criteria: According to the HUD Management Agent Handbook 4381.5 Section 6.5 Contracting Guidelines when an owner/agent is contracting for goods or services involving project income, an agent is expected to solicit written cost estimates from at least three contractors for any contract, ongoing supply or service which is expected to exceed $10,000 per year. Cause: Management decided to utilize the contractor referred by the insurance company without regard to the HUD Management Agent Handbook guidelines. Effect: The Project procured services that did not comply with HUD regulations. Recommendation: I recommend management comply with all HUD rules and regulations regarding procurement.

Corrective Action Plan

2022 ?2 No Bids Provided Condition: Management failed to provide bids for procured services that exceeded $10,000 or more. Criteria: According to the HUD Management Agent Handbook 4381.5 Section 6.5 Contracting Guidelines when an owner/agent is contracting for goods or services involving project income, an agent is expected to solicit written cost estimates from at least three contractors for any contract, ongoing supply or service which is expected to exceed $10,000 per year. Cause: Management decided to utilize the contractor referred by the insurance company without regard to the HUD Management Agent Handbook guidelines. Effect: The Project procured services that did not comply with HUD regulations. Recommendation: I recommend management comply with HUD rules and regulations regarding procurement. Management Response: The damage that was caused by the fire was insured. The Insurance Company determined what they were going to pay and recommended the contractor that they approved to do the work. There were no Operating Funds used to make the repairs due to the fire. There were no economic consequences to the property and the Insurance Company took care of all of the repairs.

Categories

Procurement, Suspension & Debarment HUD Housing Programs

Other Findings in this Audit

  • 51299 2022-001
    Significant Deficiency Repeat
  • 627741 2022-001
    Significant Deficiency Repeat
  • 627742 2022-002
    Significant Deficiency

Programs in Audit

ALN Program Name Expenditures
14.181 Supportive Housing for Persons with Disabilities $2.10M
14.195 Section 8 Housing Assistance Payments Program $224,924