Finding 504681 (2023-002)

Material Weakness
Requirement
I
Questioned Costs
-
Year
2023
Accepted
2024-11-05

AI Summary

  • Core Issue: The District failed to check if a contractor was suspended or debarred before signing a service contract.
  • Impacted Requirements: This violates 2 CFR 180.30, which mandates checks on contractors' eligibility for federal procurement.
  • Recommended Follow-Up: Implement procedures to verify contractor status before any future contracts are signed.

Finding Text

Finding 2023-002 Procurement and Suspension and Debarment ALN 21.027 Coronavirus State and Local Fiscal Recovery Fund Criteria: In accordance with 2 CFR 180.30, the District is required to perform procedures to ensure that contractors are neither suspended nor debarred prior to entering into a contract to procure goods and services. This may be accomplished by checking the System for Award Management Exclusions, collecting a certification from the entity, or adding a clause or condition to the contract with the entity. Condition: For 1 out of 1 service contracts tested, we noted that the District entered into a contract without performing procedures to ensure that the entity was not suspended or debarred when service contracts are contracted outside the competitive bidding process. Cause: The District does not have adequate procedures in place to ensure controls over Federal Procurement and Suspension and Debarment compliance requirements are operating effectively. Effect: Adequate internal controls are not in place over Federal Procurement and Suspension and Debarment compliance requirements. Questioned Costs: None. Recommendation: Procedures should be implemented to ensure that contractors are neither suspended nor debarred prior to entering into a contract. Management’s Response: The District agrees with the finding and has implemented procedures to ensure all future vendor contracts are not suspended and debarred prior to contracting with them.

Corrective Action Plan

The Conservation District has updated policies and implemented procedures for the future to ensure all future vendor contracts are not suspended and/or debarred to contracting with them.

Categories

Procurement, Suspension & Debarment

Other Findings in this Audit

  • 504682 2023-002
    Material Weakness
  • 1081123 2023-002
    Material Weakness
  • 1081124 2023-002
    Material Weakness

Programs in Audit

ALN Program Name Expenditures
66.204 Multipurpose Grants to States and Tribes $250,000
21.027 Coronavirus State and Local Fiscal Recovery Funds $145,532
66.460 Nonpoint Source Implementation Grants $136,087
66.964 Chesapeake Bay Program Implementation, Regulatory/accountability and Monitoring Grants $57,022