Material Weakness
Requirement
I
Questioned Costs
$1
Year
2024
Accepted
2024-10-23
Audit: 325673
Organization: Barre Housing Authority (VT)
Auditor: Marcum LLP

AI Summary

  • Core Issue: Lack of proper documentation for vendor procurement, leading to potential noncompliance with procurement policies.
  • Impacted Requirements: Failure to obtain and maintain at least two price quotes for contracts between $10,000 and $50,000, risking higher costs.
  • Recommended Follow-Up: Establish clear policies and procedures to ensure compliance with procurement requirements and improve documentation practices.

Finding Text

2024-001 – PROCUREMENT, SUSPENSION, AND DEBARMENT Material Weakness/Material Noncompliance U.S. Department of Housing and Urban Development CFDA #: 14.850 – Public and Indian Housing CRITERIA Any small purchase or contract, greater than $10,000 ($2,000 if Davis-Bacon rules apply) but not exceeding $50,000, may be made in accordance with the small purchase procedures outlined in this section. BHA Staff seeking prospective purchase, to be funded within the current year’s operating or capital budget they manage, should solicit a minimum of two price quotes, oral or written, if available from prospective contractors, through a competitive Request for Proposal (RFP) process by phone, fax or email. Results of this process, including bid selection recommendation and related justification are then presented to the CO who will make the award to the entity with the lowest acceptable bid and/or greatest value. CONDITION We identified 2 instances in which sufficient documentation was not maintained to support the procurement of the vendor. CAUSE Documentation of procurement decisions was not sufficiently maintained. EFFECT The Authority has not ensured that it is receiving the most competitive prices or rates for services that have been procured, which may have resulted in unnecessary additional costs to the Authority. QUESTIONED COSTS Known Questioned Costs - $98,518 representing the aggregate payments to these two vendors. CONTEXT All purchases are required to be made within the Authority’s procurement policy. There were approximately 27 vendors paid in excess of the micro purchase threshold. REPEAT FINDING Not a repeat finding. RECOMMENDATION We recommend that the Authority develop and implement sufficient policies and procedures which provides for compliance with the Procurement, Suspension, and Debarment requirements of the Uniform Guidance. AUDITEE’S RESPONSE AND PLANNED CORRECTIVE ACTION See Corrective Action Plan.

Corrective Action Plan

2024-001 - Procurement, Suspension, and Debarment Auditee's Response and Planned Corrective Action: Prior to FYE 03/31/2025 the Barre Housing Authority will be soliciting quotes from at least three flooring companies to ensure that we are getting the best prices possible when installing new flooring. We will also be putting our pest control services out to bid and getting that under a new and current contract to ensure we are getting a competitive price for these services. Barre Housing Authority will avoid this situation in the future by doing a better job of maintaining our contract register , which will ensure that contracts do not continue after expiring. Lastly, we will be reviewing our procurement policy to see if it is still reasonable for the times. With the cost of everything rising our limits may be set too low. Planned Implementation Date of Corrective Action: March 31, 2025 Person Responsible for Corrective Action: Jaime Chioldi, Executive Director

Categories

Questioned Costs Procurement, Suspension & Debarment

Other Findings in this Audit

  • 1079981 2024-001
    Material Weakness

Programs in Audit

ALN Program Name Expenditures
14.850 Public Housing Operating Fund $1.69M
14.872 Public Housing Capital Fund $1.60M