Finding 503424 (2024-003)

Significant Deficiency Repeat Finding
Requirement
A
Questioned Costs
-
Year
2024
Accepted
2024-10-22

AI Summary

  • Core Issue: There is a significant deficiency in timely work order completion, with 54 out of 120 work orders lacking documentation.
  • Impacted Requirements: Compliance with HUD's requirement for timely completion of work orders is not being met.
  • Recommended Follow-Up: Management should enhance internal controls and procedures to ensure timely completion of work orders.

Finding Text

Finding No. 2024-003: Timely Work Order Completion (Significant Deficiency) Federal Agency: U.S. Department of Housing and Urban Development Federal Program Title: Supportive Housing for Persons with Disabilities (Section 811) Federal Assistance Listing Number: 14.181 Compliance Requirement: Activities allowed or unallowed Statement of condition During the year ended June 30, 2024, management was unable to provide supporting documentation regarding timely completion of 54 of 120 work orders selected. Criteria HUD projects are required to complete work orders timely. Cause The Organization did not have sufficient controls in place to ensure the timely completion of work orders as required by HUD. Effect Significant repairs could be delayed and repairs could be falsified or duplicated. Recommendation Management should continue to review and enhance its internal controls and procedures over work orders to ensure they are completed on a timely basis. Identification of repeat finding The finding is a repeat of Finding No. 2023-004. Auditor non-compliance code S - Internal control deficiencies Questioned costs None Finding resolution status In process

Corrective Action Plan

Reporting views of responsible officials and planned corrective actions The Organization will enhance its controls to actively monitor the work order system to ensure appropriate repairs are being completed in a timely manner.

Categories

HUD Housing Programs Significant Deficiency Internal Control / Segregation of Duties

Other Findings in this Audit

  • 503422 2024-001
    Material Weakness Repeat
  • 503423 2024-002
    Material Weakness Repeat
  • 503425 2024-001
    Material Weakness Repeat
  • 503426 2024-002
    Material Weakness Repeat
  • 503427 2024-003
    Significant Deficiency Repeat
  • 1079864 2024-001
    Material Weakness Repeat
  • 1079865 2024-002
    Material Weakness Repeat
  • 1079866 2024-003
    Significant Deficiency Repeat
  • 1079867 2024-001
    Material Weakness Repeat
  • 1079868 2024-002
    Material Weakness Repeat
  • 1079869 2024-003
    Significant Deficiency Repeat

Programs in Audit

ALN Program Name Expenditures
14.218 Community Development Block Grants/entitlement Grants $344,645
14.181 Supportive Housing for Persons with Disabilities $56,961