AI Summary

  • Core Issue: The Project missed the 90-day deadline to submit audited financial statements to HUD.
  • Impacted Requirements: Compliance with the Regulatory Agreement for timely financial reporting.
  • Recommended Follow-Up: Strengthen internal controls and ensure the audit team is established to meet future deadlines.

Finding Text

Federal Program – Mortgage Insurance for the Purchase or Refinancing of Existing Multifamily Housing Projects – HUD Project No. 121-11155 Assistance Listing Number 14.155 Housing and Urban Development Program Year 2023–2024 Criteria or Specific Requirement – Federal Financial Reporting Condition – The Project failed to file the required audited financial statements to HUD via the Real Estate Assessment Center (REAC) portal within 90 days, as required under the Regulatory Agreement. The Project is responsible for submitting the audited financial statements and supplementary information on time, reporting all required information on its reports, and establishing internal controls to ensure such reports are submitted within federal requirements. Questioned Costs – N/A Context – The Project did not submit the required audited financial statements in accordance with the 90-day deadline under the Regulatory Agreement for its mortgage payable. The audited financial statements were not issued until 11 days after the requirement. Effect – The Project was not compliant with the 90-day audit deadline under the Regulatory Agreement for its mortgage payable. Cause – Due to staffing turnover and other changes at the Project, the audited financial statements were not submitted timely as certain items were still being completed as a part of the audit process. Identification as a Repeat Finding, if Applicable – N/A Recommendation – The Project should ensure the design and appropriate operating effectiveness of controls surrounding the annual financial statement audit to ensure they are reported and submitted within the required time frame. Views of Responsible Officials and Planned Corrective Actions – Management has moved the accounting responsibility for the Project to an established team and will ensure that the required annual audit report is issued and filed with REAC within the 90-day deadline in the future.

Corrective Action Plan

Corrective action plan for finding 2024-001 The company recognizes that the audit for Presidio Gate Apartments missed its official filing date in 2023. The delay in submitting the reports was due to a system conversion, staffing shortages and a delay in the auditor filing the financial statements in a timely manner. We have now been on our new system for a year and have staff allocated to working on timely and accurate financial reporting. We will work with new auditors to make sure late filings are not repeated. This corrective plan has resulted in the timely filing of the 2024 reports. Any questions on our corrective action you can contact: Joseph Miller, Director of Finance jomiller@frontporch.net (818) 254-1414

Categories

HUD Housing Programs Reporting Procurement, Suspension & Debarment

Other Findings in this Audit

  • 1055048 2024-001
    Significant Deficiency

Programs in Audit

ALN Program Name Expenditures
14.155 Mortgage Insurance for the Purchase Or Refinancing of Existing Multifamily Housing Projects $4.69M
14.195 Section 8 Housing Assistance Payments Program $1.44M