Finding 400170 (2023-004)

Material Weakness
Requirement
I
Questioned Costs
-
Year
2023
Accepted
2024-06-06
Audit: 308306
Organization: City of Peshtigo (WI)

AI Summary

  • Core Issue: The City failed to verify vendor suspension and debarment status before contracting, leading to a material weakness in internal controls.
  • Impacted Requirements: Compliance with 2 CFR Part 200, which mandates proper procurement and vendor checks.
  • Recommended Follow-Up: Establish robust internal controls to ensure all potential contractors are reviewed against the suspension and debarment list.

Finding Text

2023-004 – Federal Grants Management - Procurement Policy – Suspension and Debarment Federal Agency: U.S. Department of Treasury Federal Program Name: Coronavirus State and Local Fiscal Recovery Funds Assistance Listing Number: 21.027 Federal Award Identification Number and Year: SLFRP0135 – 2021 Pass-Through Agency: Wisconsin Department of Administration Pass-Through Number(s): ARPA-NIF-072 Award Period: March 3, 2021 through December 31, 2024 Type of Finding: • Material Weakness in Internal Control over Compliance and Other Matter Criteria or specific requirement: 2 CFR Part 200 Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Award requires compliance with the provisions of procurement, suspension, and debarment. The City should have internal controls designed to ensure compliance with those provisions. Condition: The City did not follow controls related to ensuring suspension and debarment status was verified prior to entering into contract with vendors. Questioned Costs: None Context: During our testing, it was noted that the City was not reviewing vendors prior to entering into a contract with a vendor to ensure the vendor was not on the suspended or debarred vendor list maintained by the General Services Administration. Cause: The City was unaware the contractors were not being reviewed to ensure they were not suspended or debarred. Effect: The auditor noted no instances of noncompliance with the provisions of procurement, suspension, and debarment; however, the lack of internal controls over these compliance requirements provides an opportunity for noncompliance. Repeat Finding: The finding is not a repeat of a finding in the immediately prior year. Recommendation: We recommend the City design controls to ensure an adequate review process is in place to review potential contractors to determine they are not suspended or debarred. Views of responsible officials: There is no disagreement with the audit finding.

Categories

Procurement, Suspension & Debarment

Other Findings in this Audit

  • 400166 2023-004
    Material Weakness
  • 400167 2023-005
    Significant Deficiency
  • 400168 2023-004
    Material Weakness
  • 400169 2023-005
    Significant Deficiency
  • 400171 2023-005
    Significant Deficiency
  • 976608 2023-004
    Material Weakness
  • 976609 2023-005
    Significant Deficiency
  • 976610 2023-004
    Material Weakness
  • 976611 2023-005
    Significant Deficiency
  • 976612 2023-004
    Material Weakness
  • 976613 2023-005
    Significant Deficiency

Programs in Audit

ALN Program Name Expenditures
21.027 Covid-19: Neighborhood Investment Fund Grant $744,921
21.027 Covid-19: American Rescue Plan Act $301,730
15.916 Land and Water Conservation Fund Aids $59,349
21.027 Covid-19: Law Enforcement Agency Grant $7,490