Finding 385645 (2022-007)

Material Weakness
Requirement
N
Questioned Costs
-
Year
2022
Accepted
2024-03-27

AI Summary

  • Core Issue: The School District failed to include required wage rate clauses in contracts for federally funded projects, risking noncompliance with federal regulations.
  • Impacted Requirements: Contracts over $2,000 must comply with the Davis-Bacon Act and Copeland Anti-Kickback Act, including weekly payroll submissions and prevailing wage determinations.
  • Recommended Follow-Up: Establish controls to ensure all contracts include necessary clauses, collect certified payrolls timely, and maintain documentation to support compliance with federal wage rate requirements.

Finding Text

2 CFR Section 3474 gives regulatory effect to the Department of Education for Appendix II to 2 CFR Section 200 which states that, in addition to other provisions required by the Federal agency or non-Federal entity, all contracts made by the non-Federal entity under the Federal award must contain provisions covering the following, as applicable: (D) Davis-Bacon Act, as amended (40 U.S.C. 3141-3148). When required by Federal program legislation, all prime construction contracts in excess of $2,000 awarded by non-Federal entities must include a provision for compliance with the Davis-Bacon Act (40 U.S.C. 3141-3144 and 3146-3148) as supplemented by Department of Labor regulations (29 CFR Part 5, “Labor Standards Provisions Applicable to Contracts Covering Federally Financed and Assisted Construction”). In accordance with the statute, contractors must be required to pay wages to laborers and mechanics at a rate not less than the prevailing wages specified in a wage determination made by the Secretary of Labor. In addition, contractors must be required to pay wages not less than once a week. The non-Federal entity must place a copy of the current prevailing wage determination issued by the Department of Labor in each solicitation. The decision to award a contract or subcontract must be conditioned upon the acceptance of the wage determination. The non-Federal entity must report all suspected or reported violations to the Federal awarding agency. The contracts must also include a provision for compliance with the Copeland “Anti-Kickback” Act (40 U.S.C. 3145), as supplemented by Department of Labor regulations (29 CFR Part 3, “Contractors and Subcontractors on Public Building or Public Work Financed in Whole or in Part by Loans or Grants from the United States”). The Act provides that each contractor or subrecipient must be prohibited from inducing, by any means, any person employed in the construction, completion, or repair of public work, to give up any part of the compensation to which he or she is otherwise entitled. The non-Federal entity must report all suspected or reported violations to the Federal awarding agency. 29 CFR Section 5.5(a)(3)(ii)(A) states, in part, that a contract in excess of $2,000 which is entered into for the actual construction, alteration and/or repair of a public building or public work, or building or work financed in whole or in part from Federal funds or in accordance with guarantees of a Federal agency or financed from funds obtained by pledge of any contract of a Federal agency to make a loan, grant or annual contribution shall require a clause that the contractor shall submit weekly for each week in which any contract work is performed a copy of all payrolls to the appropriate agency if the agency is a party to the contract, but if the agency is not such a party, the contractor will submit the payrolls to the applicant, sponsor, or owner, as the case may be, for transmission to the agency. 29 CFR Section 5.6 further states, in part, agencies which do not directly enter into such contracts shall promulgate the necessary regulations or procedures to require the recipient of the Federal assistance to insert in its contracts the provisions of Section 5.5. No payment, advance, grant, loan, or guarantee of funds shall be approved by the Federal agency unless the agency ensures that the clauses required by Section 5.5 and the appropriate wage determination of the Secretary of Labor are contained in such contracts. Sound accounting practices require public officials to design and operate a system of internal control that is adequate to provide reasonable assurance over the reliability of federal information provided for federal reimbursement. In 2022, the School District undertook two projects that were subject to prevailing wage requirements. Education Stabilization Funds were utilized for these project costs. For one project, the contract documents provided for us to inspect did not include the required wage rate clauses. For the other project, the School District did not enter into a formal contract with the contractor. Evidence was provided for both projects that certified payrolls were received by the School District. Without proper controls over wage rate requirements, there is an increased risk that the School District and its contractors and subcontractors are not in compliance with applicable federal regulations. Additionally, noncompliance could result in federal funding being reduced or taken away, or other sanctions imposed by the federal grantor agency. The School District should establish (or perform existing) controls to include the required clauses of 29 CFR 5.5, particularly those concerning prevailing wage rates and the requirement that the contract shall contain required prevailing wage clauses and the contractor shall submit weekly for each week in which any contract work is performed a copy of all payrolls to (or for transmission to, where applicable) the School District, in its construction contracts (and subcontracts) greater than $2,000 that are covered by the wage rate requirements and take steps to ensure contractors (and subcontractors, if applicable) are in compliance with all labor standards by collecting the required certified payroll documentation in a timely manner. The School District should obtain the necessary information from the contractor to document compliance with the program requirements and report all suspected or reported violations to the Federal awarding agency. Further, the School District should implement procedures to ensure that copies of executed contracts are maintained to support compliance of wage rate requirements.

Categories

Matching / Level of Effort / Earmarking Subrecipient Monitoring Cash Management

Other Findings in this Audit

  • 385644 2022-007
    Material Weakness
  • 385646 2022-007
    Material Weakness
  • 962086 2022-007
    Material Weakness
  • 962087 2022-007
    Material Weakness
  • 962088 2022-007
    Material Weakness

Programs in Audit

ALN Program Name Expenditures
84.010 Title I Grants to Local Educational Agencies $953,026
10.555 National School Lunch Program $624,561
10.553 School Breakfast Program $409,409
84.367 Improving Teacher Quality State Grants $107,092
84.027 Special Education_grants to States $98,165
84.424 Student Support and Academic Enrichment Program $59,353
84.358 Rural Education $50,063
84.425 Education Stabilization Fund $15,509
84.173 Special Education_preschool Grants $7,252
10.649 Pandemic Ebt Administrative Costs $3,063