Finding 38295 (2022-001)

Significant Deficiency
Requirement
I
Questioned Costs
-
Year
2022
Accepted
2023-04-02
Audit: 37414
Organization: City of Grandview, Missouri (MO)

AI Summary

  • Core Issue: The City failed to verify that contractors were not suspended or debarred before entering into contracts funded by federal awards.
  • Impacted Requirements: Compliance with 31 CFR Section 19.300, which mandates verification checks for contractors in covered transactions.
  • Recommended Follow-Up: The City should establish procedures to ensure compliance with suspension and debarment requirements for future contracts.

Finding Text

Finding 2022-001 (Significant Deficiency): Assistance # 21.027 ? COVID-19 America Rescue Plan Act of 2021 Federal Award # and Year: MO1416-T1, 2021 Name of Federal Agency: U.S. Department of Treasury Name of Pass-Thru Agency: State of Missouri Office of Administration/Division of Accounting Type of Compliance Finding: I ? Procurement and Suspension and Debarment Condition: Prior to entering into contracts with award funds, the City did not verify that contractors were not suspended, debarred, or otherwise excluded pursuant to 31 CFR section 19.300. Criteria or Specific Requirement: Per 31 CFR Section 19.300, the City is responsible for verifying that the contractor is not excluded or disqualified from doing business before entering into a covered transaction. The City is required to perform a verification check, collect a certification, or add a clause to the contracts. Questioned Costs: None Context: For both of the contracts tested, the City did not verify contractors were not suspended or debarred. The sample size was determined based upon guidelines provided by the AICPA which is not a statistically valid sample. Cause: The City does not have a procedure in place to ensure verification checks are performed, certifications are obtained or clauses are added to contracts. Effect: Suspended or debarred contractors could be used for federal contracts. Recommendation: We recommend that the City review guidance surrounding suspending and debarment requirements and implement procedures to ensure that all requirements are met for future contracts. Management Response (Unaudited): The City will institute a policy for contracts to require a verification check, collect a certification, or add a clause to the contract.

Corrective Action Plan

The following is the corrective action plan for finding 2022-001: Views of Responsible Official: Prior to entering into contracts with award funds, the City did not verify that contractors were not suspended, debarred, or otherwise excluded pursuant to 31 CFR section 19.300. Corrective Action: Management revised The City of Grandview Federal Award Subrecipient Policy to include the requirement of subrecipient verification, thus ensuring contractors are not excluded or disqualified from doing business before entering into a covered transaction. In addition, the City will conduct a verification check on any recipients of American Recovery Plan Act (ARPA) funding. Responsible Staff: Kirk Decker, Assistant City Administrator / Director of Finance Anticipated Completion Date: March 2023 (policy already revised)

Categories

Procurement, Suspension & Debarment

Other Findings in this Audit

  • 614737 2022-001
    Significant Deficiency

Programs in Audit

ALN Program Name Expenditures
20.205 I-49 Outer Roadway Conversion Project $6.69M
21.027 Covid-19 - American Rescue Plan Act of 2021 $1.16M
20.205 Mo 150 From Byars Road to Kelly Road $30,811
20.301 Raytown Road Bridge Replacement Study Dnr $19,191
93.439 Bike Walk Kc (community Health and Wellness) $18,675
20.600 Hazardous Moving Violations $14,451
20.616 Impaired Drivers - Dwi Saturation Enforcement $10,562
16.738 Edward Byrne Memorial Justice Assistance Grant Program $9,636
20.616 Youth Seat Belt Enforcement - Modot $6,961
16.607 Bulletproof Vest Partnership Program $4,010
20.607 Youth Alcohol Enforcement Campaign $3,534
20.607 Holiday Dwi $1,732
20.616 Child Passenger Safety Enforcement Campaign $198