Finding 381197 (2023-003)

Material Weakness
Requirement
I
Questioned Costs
$1
Year
2023
Accepted
2024-03-19

AI Summary

  • Core Issue: UPM made payments totaling $100,406.71 for goods/services not received and lacked necessary documentation to verify vendor eligibility.
  • Impacted Requirements: Non-compliance with federal regulations on procurement suspension and debarment, leading to improper payments.
  • Recommended Follow-Up: Reinforce payment procedures, ensure vendor verification against suspension lists, and reimburse the questioned amount to the U.S. Department of Education.

Finding Text

HEERF INSTITUTIONAL AID SCHEDULE OF FINDINGS AND QUESTIONED COSTS (CONTINUE) YEAR ENDED JUNE 30, 2023 PROCUREMENT SUSPENSION AND DEBARMENT FINDING NO. 2023-003 – PROCUREMENT SUSPENSION AND DEBARMENT CRITERIA Suspension and Debarment Schools are prohibited from contracting with or making subawards under covered transactions to parties that are suspended or debarred. “Covered transactions” include contracts for goods and services awarded under a non-procurement transaction (e.g., grant or cooperative agreement) that are expected to equal or exceed $25,000 or meet certain other criteria as specified in 2 C.F.R.§ 180.220. All non-procurement transactions entered by a passthrough entity (i.e., subawards to subrecipients), irrespective of award amount, are considered covered transactions, unless they are exempt as provided in 2 C.F.R. § 180.215. When a school enters into a covered transaction with an entity at a lower tier, the school must verify that the entity, as defined in 2 C.F.R. § 180.995 and agency adopting regulations, is not suspended or debarred or otherwise excluded from participating in the transaction. This verification may be accomplished by (1) checking the System for Award Management Exclusions maintained by the General Services Administration and available at https://www.sam.gov/SAM/ (click on Search Record, then click on Advanced Search- Exclusions) (Note: The OMB guidance at 2 C.F.R. part 180 and agency implementing regulations still refer to the System for Award Management Exclusions as the Excluded Parties List System), (2) collecting a certification from the entity, or (3) adding a clause or condition to the covered transaction with that entity (2 C.F.R. § 180.300). Schools receiving contracts from the federal government are required to comply with the contract clause at FAR 52.209-6 before entering into a subcontract that will exceed $30,000, other than a subcontract for a commercially available off-the-shelf item. Criteria: 2 C.F.R. §§ 200.318 through 200.326 2 C.F.R. Part 180 48 C.F.R. Subpart 2.1 48 C.F.R. § 9.405-2(b) 48 C.F.R. § 52.209-6 HEERF INSTITUTIONAL AID SCHEDULE OF FINDINGS AND QUESTIONED COSTS (CONTINUE) YEAR ENDED JUNE 30, 2023 PROCUREMENT SUSPENSION AND DEBARMENT FINDING NO. 2023-003 – PROCUREMENT SUSPENSION AND DEBARMENT (CONTINUE) CRITERIA (CONTINUE) Improper payment means: (1) Any payment that should not have been made or that was made in an incorrect amount under statutory, contractual, administrative, or other legally applicable requirements. (i) Incorrect amounts are overpayments or underpayments that are made to eligible recipients (including inappropriate denials of payment or service, any payment that does not account for credit for applicable discounts, payments that are for an incorrect amount, and duplicate payments). An improper payment also includes any payment that was made to an ineligible recipient or for an ineligible good or service, or payments for goods or services not received. Note 1 to paragraph (1)(i) of this definition. Applicable discounts are only those discounts where it is both advantageous and within the agency's control to claim them. (ii) When an agency's review is unable to discern whether a payment was proper as a result of insufficient or lack of documentation, this payment should also be considered an improper payment. When establishing documentation requirements for payments, agencies should ensure that all documentation requirements are necessary and should refrain from imposing additional burdensome documentation requirements. Code of Federal regulations Title II Subtitle A Chapter II Part 200 Subpart A-Acronyms Section 200.1 HEERF INSTITUTIONAL AID SCHEDULE OF FINDINGS AND QUESTIONED COSTS (CONTINUE) YEAR ENDED JUNE 30, 2023 PROCUREMENT SUSPENSION AND DEBARMENT FINDING NO. 2023-003 – PROCUREMENT SUSPENSION AND DEBARMENT (CONTINUE) CONDITION We examined one hundred percent (100%) of the disbursed made and charged to HEERF Instutional Aid for the fiscal year 2022-2023 and noted the following: 1) UPM did not have documentation related Schools are prohibited from contracting with or making subawards under covered transactions to parties that are suspended or debarred. 2) UPM made five (5) payments for $100,406.71 in advance for goods or services not received at the disbursement date. EFFECT UPM did not comply with the regulations and internal controls procedures to made disbursements before received goods or services. QUESTIONED COSTS $100,406.71 CAUSE The institution did not follow the institutional procedures to make disbursements before received goods or services according to regulations and institution procedures. RECOMMENDATION The Institution should reinforce the established procedures and adhere to them before any payment is made for goods or services. The amount of $100,406.71 should be reimbursed to the U.S. Department of Education. In addition, UPM should be included in its procedures steps to adopting regulations, to verify that the vendor entity is not suspended or debarred or otherwise excluded from participating in the transaction. VIEWS OF RESPONSIBLE OFFICIALS See the Corrective Action Plan for details of action required.

Corrective Action Plan

FIDING NO. 2023-003 PROCUREMENT SUSPENSION AND DEBARMENT CONDITION We examined one hundred percent (100%) of the disbursed made and charged to HEERF Institutional Aid for the fiscal year 2022-2023 and noted the following: 1) UPM did not have documentation related Schools are prohibited from contracting with or making subawards under covered transactions to parties that are suspended or debarred. 2) UPM made five (5) payments for $100,406.71 in advance for goods or services not received at the disbursement date. RECOMMENDATION The Institution should reinforce the established procedures and adhere to them before any payment is made for goods or services. The amount of $100,406.71 should be reimbursed to the U.S. Department of Education. In addition, UPM should be included in its procedures steps to adopting regulations, to verify that the vendor entity is not suspended or debarred or otherwise excluded from participating in the transaction. Corrective Action Plan: The UPM requested the documents from potential vendors that authorized them to do business in Puerto Rico. The selected company, Vitaltek, provided documents showing that it was established and compliant with the law, precisely the evidence that they were not debarred or suspended. The UPM has a procurement process titled " Reglamento para la Adquisici6n de Equipos, Materiales y Servicios No Personales de la Universidad Pentecostal MIZPA" that states the process for verifying debarment and suspension. Prepayments The UPM has analyzed each prepayment, and we have evidence that the services, equipment. and materials have been received. In addition to having the purchase orders, contract, and invoices, we have the equipment in our facilities in good condition and inspected per our internal procedures, titled "Reglamento para la Administraci6n de Propiedad Mueble (Equipo) de la Universidad Pentecostal Mizpa." Vitaltek was the only company that provided a quote and was selected due to the COVID-19 emergency. Their purchase condition required a prepayment for ordering and obtaining products. Regarding the Service Contract for the photocopiers, we recognize that it was paid in advance; however, to date, all services related to this contract that we have required have been offered in compliance with each of the clauses and agreements signed. The acquisition of this type of equipment comes with a multiyear plan and maintenance services included in the package, which is the industry standard and necessary for the institution's administrative and academic operations. Understanding the seriousness of the correct administration of these funds, the Dean of Administration will periodically evaluate compliance with any contract. If it is not complied with, we will proceed through legal action to quickly recover these funds. The UPM understands that it should not reimburse this money to the United States Department of Education because there is sufficient evidence to demonstrate that the funds have been used within legal parameters, that they have strengthened the University in academic and administrative and that from now on we will observe the following to comply with such an essential and necessary reservation. Corrective action plan to follow: All employees. including those in the office of the presidency, have been finally and firmly alerted that advance payments should be avoided or only considered in emergency situations. All employees authorized to reach contractual agreements will be trained on this topic, and the internal procedures will be reviewed and edited to address prepayments and emergency processes. We will appoint an employee in charge of managing all compliance documentation so that, together with the Dean of Administration and Finance, they can locate and group all the relevant standards and regulatory procedures and have the power to guide so that each of its recommendations is willingly observed. This will be supported by the requirements that always accompany each award. In addition, these officers will have the power to make external consultations with professionals familiar with these matters.

Categories

Questioned Costs Procurement, Suspension & Debarment Subrecipient Monitoring

Other Findings in this Audit

  • 381196 2023-002
    Significant Deficiency
  • 957638 2023-002
    Significant Deficiency
  • 957639 2023-003
    Material Weakness

Programs in Audit

ALN Program Name Expenditures
84.425e Higher Education Emergeny Relief Fund Student Portion $655,687
84.425F Higher Education Emergency Relief Fund Institutioanl Portion $570,562
84.063 Federal Pell Grant Program $415,842
84.007 Federal Supplemental Educational Opportunity Grant $8,638
84.033 Federal Work Study Program $7,139
97.036 Disater Grant Public Assistance Presidencially Declared Disasters $43