Personnel to Effect Change: Finance Director (Steve Baugher), Capital Projects & Grant Accountant
(Linda Wertman), Grants Manager (Catherine Rigby), and City Engineer (Interim Chris Beatty)
City Response and Corrective Action Plan: Fiscal year 2022-23 was a challenging year for the City of
Newport due to staff turnover and vacancies for key positions in Engineering, Public Works and Finance.
Processes were in place to ensure that vendors were not on the suspended or debarred list prior to
awarding contracts. However, due to key staff turnover, the documentation was not available to verify
that the process was followed, The Finance Department, Engineering, and Grant Manager will work on
a checklist to make sure all required written documentation is obtained. The written documentation
will be centrally kept by the Capital Projects and Grant Accountant with the awarded contract before
executing the contract. The checklist will include that the suspended and debarred list is checked to
make sure the awardee is not on the list and retain documentation of the list being checked.
Anticipated Completion Date(s): March 31, 2024