Finding 37158 (2022-003)

Material Weakness
Requirement
N
Questioned Costs
-
Year
2022
Accepted
2023-03-28

AI Summary

  • Core Issue: The Authority failed to properly withhold Housing Assistance Payments (HAP) for units that did not pass inspections, violating HUD regulations.
  • Impacted Requirements: Compliance with HQS inspection standards, specifically the timely abatement of HAP payments for units with deficiencies.
  • Recommended Follow-Up: Enhance training for staff and implement a review process to ensure adherence to HUD rules and proper HAP payment abatement.

Finding Text

2022-003 Special Tests and Provisions: HCV Failed Inspections Section 8 Housing Voucher Cluster (Section 8): Section 8 Housing Choice Vouchers Program ? CFDA Number 14.871 Mainstream Vouchers ? CFDA Number 14.879 Material Weakness in Internal Control, Material Noncompliance Condition: Out of a total failed inspection population of approximately 540 units, 25 failed inspections were selected for testing. Exceptions were noted as follows: ? 1 Inspection and HAP abatement error where the tenant?s unit did not pass inspection and HAP payments were not withheld from July 2022 through February 2023. ? 1 HAP abatement error where the Authority pro-rated the HAP payment for August 2022 and abated the HAP payment for September through November 2022, but subsequently, whether due to a user or system error, HAP payments were paid out for the months from September through November 2022. ? 1 HAP abatement error where the Authority pro-rated the HAP payment for January & May 2022 and abated the HAP payment for February through April 2022, but subsequently, whether due to a user or system error, HAP payments were paid out for the months from January through May 2022. ? 1 HAP abatement error where the Authority didn't pro-rate the HAP payment withholding for June & December 2022 nor withhold the HAP payment for the month of July 2022. The Authority properly withheld the HAP payments for the months of August, September, October, and November 2022. Criteria: For units under HAP contract that fail the HQS inspection, the PHA must require the owner to correct any life threatening HQS deficiencies within 24 hours after the inspections and all other HQS deficiencies within 30 calendar days or within a specified PHA-approved extension. If the owner does not correct the cited HQS deficiencies within the specified correction period, the PHA must stop (abate) HAPs beginning no later than the first of the month following the specified correction period or must terminate the HAP contract. Questioned Costs: None. Effect: The Authority is not in compliance with applicable HUD regulations and HQS policies and as a result HAP payments were not properly abated which are designed to assure that landlords complete unit repairs timely to provide safe housing for tenants. Cause: Procedures to ensure compliance with all of the HUD requirements were not being carefully followed. Auditor?s Recommendation: The Authority should review procedures and increase training to employees and reviewers to ensure that the Authority is in compliance with HUD rules for HQS inspections. In addition, the Authority should implement a review procedure to make sure that HAP payments are properly abated when required. Views of Responsible Officials of the Auditee: The Authority agrees with the finding and has taken corrective action. See the ?Action Taken? on the Corrective Action Plan.

Categories

HUD Housing Programs Material Weakness Internal Control / Segregation of Duties Special Tests & Provisions

Other Findings in this Audit

  • 37144 2022-001
    Material Weakness Repeat
  • 37145 2022-002
    Material Weakness
  • 37146 2022-003
    Material Weakness
  • 37147 2022-001
    Material Weakness Repeat
  • 37148 2022-002
    Material Weakness
  • 37149 2022-003
    Material Weakness
  • 37150 2022-001
    Material Weakness Repeat
  • 37151 2022-002
    Material Weakness
  • 37152 2022-003
    Material Weakness
  • 37153 2022-001
    Material Weakness Repeat
  • 37154 2022-002
    Material Weakness
  • 37155 2022-003
    Material Weakness
  • 37156 2022-001
    Material Weakness Repeat
  • 37157 2022-002
    Material Weakness
  • 37159 2022-004
    Material Weakness Repeat
  • 37160 2022-005
    Material Weakness Repeat
  • 37161 2022-004
    Material Weakness Repeat
  • 37162 2022-005
    Material Weakness Repeat
  • 613586 2022-001
    Material Weakness Repeat
  • 613587 2022-002
    Material Weakness
  • 613588 2022-003
    Material Weakness
  • 613589 2022-001
    Material Weakness Repeat
  • 613590 2022-002
    Material Weakness
  • 613591 2022-003
    Material Weakness
  • 613592 2022-001
    Material Weakness Repeat
  • 613593 2022-002
    Material Weakness
  • 613594 2022-003
    Material Weakness
  • 613595 2022-001
    Material Weakness Repeat
  • 613596 2022-002
    Material Weakness
  • 613597 2022-003
    Material Weakness
  • 613598 2022-001
    Material Weakness Repeat
  • 613599 2022-002
    Material Weakness
  • 613600 2022-003
    Material Weakness
  • 613601 2022-004
    Material Weakness Repeat
  • 613602 2022-005
    Material Weakness Repeat
  • 613603 2022-004
    Material Weakness Repeat
  • 613604 2022-005
    Material Weakness Repeat

Programs in Audit

ALN Program Name Expenditures
14.871 Section 8 Housing Choice Vouchers $11.44M
14.850 Public and Indian Housing $3.74M
14.872 Public Housing Capital Fund $1.52M
14.879 Mainstream Vouchers $888,003
14.871 Ehv Section 8 Housing Choice Vouchers $301,932
14.850 Covid-19 Public and Indian Housing $118,463
14.871 Covid-19 Section 8 Housing Choice Vouchers $92,481
14.896 Family Self-Sufficiency Program $70,638
14.870 Resident Opportunity and Supportive Services - Service Coordinators $53,848
14.879 Covid-19 Mainstream Vouchers $5,952