  • Issue: The audit report was submitted late, violating 2 CFR section 200.512(a).
  • Impact: Late submission risks federal and state funding suspension.
  • Next Steps: Management is implementing a plan to keep financial records current and ensure timely audits.

Finding Text

2022-001 Late Submission Criteria or Specific Requirement: 2 CFR section 200.512(a) requires the reporting package and data collection form to be submitted to the Federal Audit Clearinghouse the earlier of 30 calendar days after the reports are received from auditor or nine months after the end of the audit period. Condition: The fiscal year audit and reporting package is being submitted after the required due date. Effect: There is a potential for suspension or cessation of federal and/or state funding. Cause: Turnover in fiscal and management personnel resulted in delays in preparing for the October 31, 2022 audit and providing audit documentation in a timely manner. Repeat: No Auditor's Recommendations: Southern Oregon Child & Family Council, Inc. should take steps to ensure that its financial records are maintained on a current basis, reconciled timely, and audited within nine months after year end. View of Responsible Officials: Management agrees with the finding and has developed and begun implementation of a corrective action plan.

Categories

Procurement, Suspension & Debarment Reporting

Other Findings in this Audit

  • 36530 2022-001
    Material Weakness
  • 612972 2022-001
    Material Weakness
  • 612973 2022-001
    Material Weakness

Programs in Audit

ALN Program Name Expenditures
93.600 Head Start $11.47M
10.558 Child and Adult Care Food Program $454,591