Finding 32301 (2022-004)

-
Requirement
B
Questioned Costs
-
Year
2022
Accepted
2023-03-30
Audit: 35785
Organization: Lakewood Theatre Company (OR)

AI Summary

  • Core Issue: Lakewood Theatre Company's procurement policies do not comply with 2 CFR Part 200.318(a).
  • Impacted Requirements: Lack of written procedures increases the risk of unallowable costs being charged to the program.
  • Recommended Follow-Up: Management should update their procurement procedures to align with federal requirements.

Finding Text

Criteria: 2 CFR Part 200.318(a) requires the entity have written procurement policies and procedures. Condition: While Lakewood Theatre Company has internal procurement policies and procedures, these do not meet the requirements of 2 CFR Part 200.318(a). Cause: Administration did not have written procedures over procurement which meet the requirements of 2 CFR Part 200.318(a). Effect: Unallowable costs could be charged to the program. Questioned Costs: None Recommendations: Management should modify their written procedures as required by 2 CFR Part 200.318(a). Views of Responsible Officials: Management notes that, as this is their first time receiving significant federal funding and this was one-time emergency funding rather than an ongoing award, they do not have these procedures in writing. However, they reviewed the award guidelines, obtained multiple bids, and adhered to their internal conflict of interest policy in the selection of vendors. While they do not anticipate receiving federal funding in the future, if this does occur, they will develop written procedures at that point.

Corrective Action Plan

Response: Management notes that, as this is their first time receiving significant federal funding and this was one-time emergency funding rather than an ongoing award, they do not have procurement procedures in writing which adhere to 2 CFR Part 200.318(a). However, they adhered to their internal written procurement procedures and conflict of interest policies, followed the award guidelines, and obtained multiple bids in the selection of vendors for contracted services. Action to be taken: Management notes that, as this was one-time emergency funding rather than an ongoing award, they do not anticipate receiving federal funding in the future. As such, they do not intend to document these procedures in writing at this point. However, if they apply for federal funding again in the future, they will develop written procedures at that point. Responsible Person: Andrew Edwards, Executive Director

Categories

Procurement, Suspension & Debarment Allowable Costs / Cost Principles

Other Findings in this Audit

Programs in Audit

ALN Program Name Expenditures
59.075 Covid-19 - Shuttered Venue Operators Grant Program $1.11M