Finding 2325 (2023-003)

Significant Deficiency
Requirement
L
Questioned Costs
-
Year
2023
Accepted
2023-11-22
Audit: 3982
Organization: Holt County (NE)

AI Summary

  • Core Issue: Holt County failed to implement effective internal controls, leading to inaccuracies in the Project and Expenditure report for SLFRF funds.
  • Impacted Requirements: Compliance with federal regulations regarding internal controls and accurate reporting as mandated by the U.S. Department of the Treasury.
  • Recommended Follow-Up: Establish procedures for accurate reporting, including training on federal requirements and a thorough review process by an independent individual.

Finding Text

Program - AL 21.027 – COVID-19 – Coronavirus State and Local Fiscal Recovery Funds – Reporting Grant Number & Year - SLFRP2377, March 3, 2021, through December 31, 2024 Federal Grantor Agency - U.S. Department of the Treasury Criteria - Title 2 of the U.S. Code of Federal Regulations (CFR) § 200.303 (January 1, 2023) states the following, in relevant part: The non-Federal entity must: (a) Establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with Federal statutes, regulations, and the terms and conditions of the Federal award. These internal controls should be in compliance with guidance in “Standards for Internal Control in the Federal Government” issued by the Comptroller General of the United States or the “Internal Control Integrated Framework”, issued by the Committee of Sponsoring Organizations of the Treadway Commission (COSO). The U.S. Department of the Treasury adopted the Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards in 2 CFR § 1000.10 (January 1, 2023), which states the following: Except for the deviations set forth elsewhere in this Part, the Department of the Treasury adopts the Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards, set forth at 2 CFR part 200. The U.S. Department of the Treasury issued “Compliance and Reporting Guidance” and frequently asked questions, which specify the reporting requirements related to Coronavirus State and Local Fiscal Recovery Funds. A good internal control plan includes establishing effective internal controls through written policies and procedures to ensure Federal reporting requirements are completed accurately. Such plan should include, among other things, appropriate training on Federal reporting requirements and require a documented, detailed review of each report to be completed by a knowledgeable individual, who did not prepare the report, prior to submission. Condition - Holt County did not implement effective internal controls to ensure that the reporting requirements of the Coronavirus State and Local Fiscal Recovery Funds (SLFRF) were completed accurately. The Project and Expenditure report submitted on April 28, 2023, did not contain accurate information for multiple expenditure and obligations categories. Repeat Finding - No Questioned Costs - None Statistical Sample - No Context - The following table summarizes the variances noted: Cause - Lack of procedures and knowledge relating to Federal reporting requirements. Effect - Inaccurate information was reported to the U.S. Department of the Treasury on the 2023 Project and Expenditure report. Additionally, there is an increased risk the County is not in compliance with the reporting requirements set by the U.S Department of the Treasury. Recommendation - We recommend the County implement procedures to ensure Federal reporting requirements are completed accurately. Such procedures could include, among other things, appropriate training on Federal reporting requirements and a documented review by a knowledgeable individual who was not involved in the preparation of the report. View of Officials - Holt County will create a spreadsheet that will track expenditures and obligations.

Corrective Action Plan

Holt County will create a spreadsheet that will track expenditures and obligations.

Categories

Allowable Costs / Cost Principles Reporting Matching / Level of Effort / Earmarking Internal Control / Segregation of Duties

Other Findings in this Audit

  • 2324 2023-002
    Significant Deficiency
  • 578766 2023-002
    Significant Deficiency
  • 578767 2023-003
    Significant Deficiency

Programs in Audit

ALN Program Name Expenditures
21.027 Coronavirus State and Local Fiscal Recovery Funds $1.27M
97.036 Disaster Grants - Public Assistance (presidentially Declared Disasters) $317,404
93.563 Child Support Enforcement $49,610
97.042 Emergency Management Performance Grants $16,188