Finding 1240767 (2025-002)

Material Weakness Repeat Finding
Requirement
L
Questioned Costs
-
Year
2025
Accepted
2026-10-21

AI Summary

  • Issue: The Organization missed the deadline for submitting its single audit reporting package, filing it in October 2026 instead of by September 30, 2026.
  • Requirements Impacted: This late submission violates 2 U.S. CFR 200.512, which mandates timely reporting to the Federal Audit Clearinghouse.
  • Recommended Follow-Up: Enhance financial reporting procedures to ensure compliance with submission deadlines moving forward.

Finding Text

Criteria: In accordance with 2 U.S. Code of Federal Regulation (CFR) 200.512, the Organization must submit its single audit reporting package and data collection form to the Federal Audit Clearinghouse (FAC) no later than 30 days after the date of its audited financial statements or 9 months after the fiscal year end, whichever occurs earlier. Condition and Context: The federal reporting deadline for the Organization’s December 31, 2024 reporting package was September 30, 2026; however, the Organization did not issue its single audit reporting package until October 2026. Effect: Late filing has resulted in noncompliance with timely submission of financial information to grantor agencies. Cause: The Organization did not have adequate procedures to ensure a timely filing process so that it can submit its single audit reporting package to the FAC no later than nine months after fiscal-year end. Recommendation: The organization should improve its financial reporting process so that it can submit its single audit reporting package to the FAC no later than nine months after the fiscal year end. Management Response: Refer to corrective action plan.

Corrective Action Plan

Background: The delivery of the single audit was delayed due to staffing capacity constraints, competing administrative priorities, and the need for improved coordination in gathering audit documentation. AYUDA is committed to improving the audit preparation process to ensure the single audit is completed and submitted within the required timeframe. Corrective Actions: 5. Audit Planning Timeline • Action: Begin annual audit preparation earlier in the fiscal cycle, including the development of a detailed audit timeline and internal milestone deadlines. • Responsibility: Executive Management and Finance Department. • Timeline: To be implemented for the next audit cycle and maintained annually. 6. Document Preparation and Tracking • Action: Maintain a centralized audit request list and tracking system to ensure supporting documents are compiled timely and submitted to auditors as requested. • Responsibility: Finance and Administrative Staff. • Timeline: Effective immediately and ongoing. 7. Staff Training and Cross-Coordination • Action: Provide additional training and internal coordination to staff involved in grant compliance, audit support, and financial reporting responsibilities. • Responsibility: Administration and Finance Department. • Timeline: Training and coordination efforts to begin within 60 days. 8. Regular Communication with Auditors • Action: Schedule periodic status meetings with the auditors during the audit process to address open items promptly and monitor progress toward completion. • Responsibility: Finance Department. • Timeline: During each audit engagement, beginning with the next audit cycle. Conclusion AYUDA is committed to addressing these findings with urgency and transparency. Through the implementation of the corrective actions outlined above, management expects to strengthen financial oversight, improve compliance processes, and ensure timely completion of future audit requirements.

Categories

Reporting

Programs in Audit

ALN Program Name Expenditures
14.239 HOME INVESTMENT PARTNERSHIPS PROGRAM $730,149
14.913 HEALTHY HOMES PRODUCTION PROGRAM $668,102
93.268 IMMUNIZATION COOPERATIVE AGREEMENTS $184,905
93.569 LOW-INCOME HOME ENERGY ASSISTANCE $39,222
10.311 BEGINNING FARMER AND RANCHER DEVELOPMENT PROGRAM $36,833